Construction Update 5/17 thru 5/21
Posted May 17th, 2010 by evanjoseFor May 17th – May 21st, 2011, please see the following for what construction will impact.
Significant Impact(s):
- Limited parking on 17th street (see below for details)
- Traffic control revisions on Western between 16th & 17th
- Equipment Noise
Monday: (7:30am – 4:30pm)
- Prep for temporary trailer installation delivery (Fortis layout, foundations)
- Construct temporary construction driveway into site (rock trucks, front-end loader & compactor)
- Begin mass excavation of the building pad (track hoe, back hoe & rock trucks)
- Excavate for new sewer connection to the construction trailer (track hoe, back hoe)
Tuesday: (7:30am – 4:30pm)
- Delivery of Fortis construction trailers (4 over-size truck deliveries)
- Installation of construction trailers (level & anchor foundations & hook-up utilities)
- Construct temporary construction driveway into site (rock trucks, front-end loader & compactor)
- Continue mass excavation of the building pad (track hoe, back hoe & rock trucks)
- PPL – Method of Procedure coordination meeting for 17th Street existing power (10AM)
- Installation of site construction signage (Fortis)
Wednesday: (7:30am – 4:30pm)
- Installation of construction trailers (level & anchor foundations & hook-up utilities)
- Continue mass excavation of the building pad (track hoe, back hoe & rock trucks)
- NW Natural Gas – coordination meeting for gas line to be abandoned in 17th Street
- Installation of construction temp utilities – power and water (back hoe)
Thursday: (7:30am – 4:30pm)
- Construct deck and stairs at Fortis construction trailers
- Installation of construction trailers (level & anchor foundations & hook-up utilities)
- Continue mass excavation of the building pad (track hoe, back hoe & rock trucks)
- Installation of construction temp utilities – power and water (back hoe)
Friday: (7:30am – 4:30pm)
- Construct deck and stairs at Fortis construction trailers
- Installation of construction trailers (level & anchor foundations & hook-up utilities)
- Continue mass excavation of the building pad (track hoe, back hoe & rock trucks)
- Installation of construction temp utilities – power and water (back hoe)
- Excavate parking lot north of A Avenue (back hoe, front-end loader & compactor)