Significant Impact(s):

  • Limited parking on 17th street (see below for details)
  • Traffic control revisions on Western between 16th & 17th
  • Equipment Noise.

Monday:   (7:30am – 4:30pm)

  • Flaggers & traffic control on Western to sawcut/prep/pour-back for new AC paving patch (sawcutter & AC Paving trucks/equipment)
  • Fill-in & compact foundations at A Ave future parking area where old houses were demo’d (track hoe and back hoe)
  • Construct street section on 16th and A (track hoe, back hoe & rock trucks)
  • Survey & layout for site electrical re-route work

Tuesday:  (7:30am – 4:30pm)

  • Flaggers & traffic control on Western for City Water to rework water line (track hoe for digging and back hoe for compaction),
  • Fill-in & compact foundations at A Ave future parking area where old houses were demo’d (track hoe and back hoe),
  • Construct street section on 16th and A (track hoe, back hoe & rock trucks)

Wednesday:   (7:30am – 4:30pm)

  • Flaggers & traffic control on Western for City Water to rework water line and Pacific Excavation to rework storm line (track hoe for digging and back hoe for compaction),
  • Construct street section on 16th and A (track hoe, back hoe & rock trucks),
  • Start work adjacent to Halsell Hall for Pacifc Power trenching and conduit runs (track hoe/back hoe) ***NO STUDENT PARKING ON 17TH NEXT TO HALSELL***
  • Build gravel construction entry off 16th (rock trucks, front-end loader & compactor)

Thursday:       (7:30am – 4:30pm)

  • Flaggers & traffic control on Western for radius curb install at 16th and Western (concrete curb equipment)
  • Construct street section on 16th and A (track hoe, back hoe & rock trucks),
  • Start work adjacent to Halsell Hall for Pacific Power trenching and conduit runs (track hoe/back hoe) ***NO STUDENT PARKING ON 17TH NEXT TO HALSELL***
  • Gas company work at 16th and Western for gas line re-work
  • Pacific Power pole removal on 17th
  • Level/gravel pad for A Ave future parking area where old houses were demo’d (rock trucks, front-end loader & compactor)
  • Building Mass Excavation (track hoe, back hoe, dump trucks)
  • New curb install on 16th and A (concrete curb equipment)

Friday:       (7:30am – 4:30pm)

  • Flaggers & traffic control on Western for AC patch at 16th and Western (AC patch equipment)
  • Utility trenching adjacent to Halsell Hall for Pacifc Power trenching and conduit runs (track hoe/back hoe) ***NO STUDENT PARKING ON 17TH NEXT TO HALSELL***
  • Gas company work at 16th and Western for gas line re-work
  • Level/gravel pad for A Ave future parking area where old houses were demo’d (rock trucks, front-end loader & compactor)
  • Building Mass Excavation (track hoe, back hoe, dump trucks)
  • New curb install on 16th and A (concrete curb equipment)