Construction Update 5/17 thru 5/21  May 17th, 2010

For May 17th – May 21st, 2011, please see the following for what construction will impact.

Significant Impact(s):

  • Limited parking on 17th street (see below for details)
  • Traffic control revisions on Western between 16th & 17th
  • Equipment Noise

Monday:   (7:30am – 4:30pm)

  • Prep for temporary trailer installation delivery (Fortis layout, foundations)
  • Construct temporary construction driveway into site (rock trucks, front-end loader & compactor)
  • Begin mass excavation of the building pad (track hoe, back hoe & rock trucks)
  • Excavate for new sewer connection to the construction trailer (track hoe, back hoe) Read the rest of this entry »

Construction Update 5/10  May 10th, 2010

Significant Impact(s):

  • Limited parking on 17th street (see below for details)
  • Traffic control revisions on Western between 16th & 17th
  • Equipment Noise.

Monday:   (7:30am – 4:30pm)

  • Flaggers & traffic control on Western to sawcut/prep/pour-back for new AC paving patch (sawcutter & AC Paving trucks/equipment)
  • Fill-in & compact foundations at A Ave future parking area where old houses were demo’d (track hoe and back hoe)
  • Construct street section on 16th and A (track hoe, back hoe & rock trucks)
  • Survey & layout for site electrical re-route work Read the rest of this entry »