Primary construction activities for the week of 1/14/2019-1/18/2019 consist of:

Core 1- Level 4 Will have rebar and formwork set. Core 1 will also have a structural patch fix that will require jackhammering with a water wash.

Core 2- Level 3 will have rebar set, closing in formwork, and begin pouring level 3.

Core 3- Level 2 will be poured and stripped, then the forms will be moved up to level 3 and begin setting rebar.

Slab for Level 1 Air Handler Unit- will have drain rock and vapor barrier placed, then rebar for the slab will be set.

Mockups for installing steel window surrounds, backing, and weather barrier will be constructed.

Primary construction activities for the week of 10/22 thru 10/26 will consist of the following:

  • Installing asphalt walk at ODFW / West Wing
  • Installing Rebar, pouring, and stripping Continuous Footings
  • Pouring concrete and stripping at East Mat Footing (attached Images)
  • One-side formwork for Shear Walls 1, 2, and 3
  • Installing rebar at Shear Walls 4 and 5
  • Forming and installing rebar for Level 1 of Core 1
  • Forming and installing rebar for Starter Wall at Core 2 & 3

Attached Schedule

2018.10.14.OAC

The primary construction activities this week include:

Placement of rebar and pouring of concrete for the shear wall footings.

Forming, rebar placement, and pouring of concrete for the west mat footing.

Rocking and forming for the east mat footing.

Waterline shutdown for tie in at Guin Library Tuesday October 9th from 7:00am to 9:00am

Waterline shutdown for tie in at Housing and Dining Friday October 12th from 11:00am to 2:00pm.