Primary construction activities for the week of 04/01/2019 thru 04/05/2019 will consist of the following:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • East Storage Rm & Northeast Wall (Pour 4):
      • Setting wall, placing rebar, and closing formwork
    • Structural Steel
      • Zone 1:
        • Install metal decking and closure strips
      • Slab on Metal Deck
        • Zone 3 Level 3:
          • Pouring and curing deck for shore removal
        • Zone 5 & ½ Zone 4 Roof:
          • Installing rebar, top embeds, and pouring deck
        • Zone 4 Level 3:
          • Installing blockouts, down embeds, shoring, rebar, and top embeds
        • Zone 3 Level 2:
          • Installing rebar
        • Zone 3 Level 2:
          • Installing blockouts, down embeds, and shoring
        • Zone 4 Level 2:
          • Installing blockouts, down embeds, and shoring
        • Zone 5 Level 2:
          • Installing blockouts and down embeds
        • Slab on Grade
          • Zone 1:
            • Installing blockouts, edge form, importing rock / grade, installing rebar, vapor barrier and top embeds
          • Zone 2:
            • Installing blockouts, edge form, importing rock / grade
            • Digging footings and pouring grout at GL-N
            • Forming, placing rebar, and pouring footing at GL-N
            • Installing vapor barrier, stripping at GL-N, and back filling at GL-N
          • Roofing
            • Lab Wing High Roof:
              • Start forming curbs and crickets at beginning of week.

Primary construction activities for the week of 03/25/2019 thru 03/29/2019:

  • Ramp
    • North Radius Wall (Pour 2):
      • Strip formwork.
    • South Wall West (Pour 3):
      • Finish setting wall and installing rebar.
  • Structural Steel
    • East Lab Wing (Z5):
      • Finish bolting, plumbing, and welding.
      • Start installing metal decking and closure strips.
  • Slab on Metal Deck
    • West Commons Wing Roof (Z2):
      • Pouring at beginning of week
    • West Lab Wing Roof (Z3 & ½ Z4):
      • Installing rebar, top embeds, and pouring deck
    • West Lab Wing L3 (Z3):
      • Installing rebar, and top embeds
    • West Lab Wing L2 (Z3)
      • Installing blockouts, down embeds and shoring
  • Slab on Grade
    • East Commons Wing:
      • Installing sanitary sewer and storm, electrical, potable water, blockouts and edge form, and grading.
    • West Commons Wing
      • Installing electrical, potable water, sanitary sewer and storm, installing block outs and edge form, and grading.
  • Roofing
    • Lab Wing High Roof:
      • Start forming curbs and crickets at end of week.

Primary construction activities for the week of 03/18/2019 – 03/22/2019:

  • Ramp:
    • South Wall West (Pour 3):
      • Finish setting wall and installing rebar. Start closing formwork.
  • Structural Steel:
    • West Lab Wing (Z3):
      • Finish installing headed studs.
    • Center Lab Wing (Z4):
      • Continue installing metal decking and closure strips.
    • East Lab Wing (Z5):
      • Continue bolting, plumbing, and welding.
  • Slab on Metal Deck
    • West Commons Wing Roof (Z2):
      • Installing rebar and shoring.
      • Installing top embeds.
      • Pouring deck at EOW.
    • West Commons Wing L2 (Z2):
      • Pouring deck Mid-Week.
      • Curing deck.
    • West Lab Wing Roof (Z3):
      • Installing blockouts, down embeds, and shoring.
      • Start installing rebar.
    • West Lab Wing L3 (Z3):
      • Installing blockouts, down embeds, and shoring.
    • Mockup:
      • QED performing Water Test.

Primary construction activities for the week of 03/11/2019 thru 03/15/2019:

  • Ramp:
    • Pour 2 (North Radius Wall):
      • Finish stripping wall.
    • Pour 3 (South Wall West):
      • Setting wall and installing rebar.
  • Structural Steel:
    • Stair 2:
      • Finish install of handrails.
    • East Commons (Z1):
      • Finish install of metal decking and closure strips.
    • West Lab Wing (Z3):
      • Installing headed studs.
    • Center Lab Wing (Z4):
      • Finish bolting, plumbing, and welding.
      • Install metal decking and closure strips.
    • East Lab Wing (Z5):
      • Bolting, plumbing, and welding
  • Slab on Metal Deck
    • Z2 Roof:
      • Installing blockouts and down embeds
      • Installing rebar
      • Installing top embeds
    • Z2 L2:
      • Installing blockouts and down embeds
      • Installing rebar
  • Sitework & Utilities
    • Install potable and fire water laterals
  • Mockup:
    • Finish installing siding.

Primary Construction activities for the week of 2/25/2019 to 3/1/2019:

Ramp:

Storage Room South Wall- Closing formwork, pouring, and stripping.

Northwest Ramp Radius Wall- Closing formwork, pouring, and stripping.

Southwest Ramp Wall- Setting wall formwork.

Structural Steel:

Stair 2- Install clips, hangers, stairs, and handrails.

East Commons (Z1)- Installing metal decking and closure strips.

West Commons (Z2)- Bolting, plumbing, welding, and installing metal decking and closure strips.

West Lab Wing (Z3)- Bolting, plumbing, and welding

Center Lab Wing (Z4)- Bolting, plumbing, and welding

East Lab Wing (Z5)- Erecting, bolting, plumbing, and welding

Mockup:

-Finish Installing windows

-Installing Backing and Flashing on top of Green Girts

-Installing Soffits

Primary construction activities for the week of 2/18/2019 – 2/22/2019 will consist of:

Ramp- setting wall formwork, installing wall rebar, and closing formwork.

Structural Steel-

Stair 2- Installing clips, hangers, stairs, and handrails.

East Commons (Z1)- Installing metal decking and closure strips.

West Commons (Z2)- Bolting, plumbing, and welding. Installing metal decking and closure strips.

West Lab Wing (Z3)- Erecting steel, bolting, plumbing, and welding.

Center Lab Wing (Z4)- Erecting steel.

Mockup- Installing windows, green girts, and flashing behind green girts.

Primary construction activities for the week of 2/11/2019 – 2/12/2019 will consist of:

Core 1: Forming, pouring, and stripping the architectural fur wall.

Ramp: Fabricating walls and setting walls.

Structural Steel:

Stair 1: installing clips and hangers.

Stair 2: Delivery by EOW.

East Commons (Z1): Erecting steel, bolting, plumbing and welding.

West Commons (Z2): Erecting, bolting, plumbing, and welding.

West Lab Wing (Z3): Installing, shear tab clips, and erecting.

Center Lab Wing (Z4): Installing shear tab clips and misc metals.

East Lab Wing (Z5): Installing shear tab and misc metals.

Mockup: Framing, installing steel window surround, backing, weather barrier, and windows.

Primary Construction Activites for 02/04/2019-02/08/2019:

Core 1: Forming and pouring architectural fur wall.

Core 3: stripping level 4 core exterior.

Ramp: Stripping South and North footings. Fabricating walls and setting wall formwork.

Structural Steel: Stair 1- Installing stair and handrails.

Stair 2- Installing stair and handrails.

East Commons (Z1): Erecting steel, bolting, welding, and plumbing.

West Commons (Z2): Installing shear tab clips and misc. metals.

West Lab Wing (Z3): Installing Shear tab clips and misc. metals.

Mockup: Framing, installing steel window surround, backing, and weather barrier.

Primary construction activities for the week of 1/28/2019 – 2/1/2019 will consist of:

Core 1- Forming and pouring architectural fur wall.

Core 2- Level 4 will have rebar placed, formwork closed, and be poured.

Core 3- Level 4 will have rebar placed, formwork closed, and be poured.

Ramp- Forming and placing rebar, and pouring footings at the South wall.

Slab for Level 1 Air Handler Unit- pouring then striping the forms.

Mockups- Framing and sheeting.

Structural Steel- Stair 1 installing handrail.

– East Commons (Z1) installing shear tab clips. erecting steel Friday 2/10.

– West Commons (Z2) installing shear tab clips and misc. Metals.

Primary construction activities for the week of 01/21/2019- 01/25/2019 will consist of:

Core 2- Level 3 will be poured and inside core stripped, then start setting formwork and rebar for Level 4.

Core 3- Level 3 will be poured and stripped, then start setting formwork and rebar for Level 4.

Ramp- Forming and placing rebar at South Wall.

Slab for Level 1 Air Handler Unit- Install vapor barrier, forming, pour pads, and stripping pads.

Mockups- Install steel window surrounds, backing, and weather barrier.

Structural Steel- Installing clips and hangers for stair 1, and installing shear tab clips for east commons (Z1).