Primary construction activities for the week of 08/26 thru 08/30 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- High Roof Auditorium:
- Low Roof Auditorium:
- Begin installing siding
- Lab Wing Main Roof:
- Finish installing drain mat foam and rock ballast
- Begin to install the exterior concrete topping slabs
- Penthouses:
- Lab High Roof West:
- FRAMING SHEATING
- – South Elevation:
- Commons Wing – North Elevation:
- Commons Wing – East Elevation:
- Commons Wing – West Elevation:
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- Lab Wing – North Elevation:
- Finish installing beauty cap and flashing
- Lab Wing – East Elevation:
- Lab Wing – South Elevation:
- Begin installing vertical siding MWC
- Auditorium – East Elevation:
- Install glass and pressure bar
- Install vertical siding MWC
- Finish installing insulation and horizontal cleat
- Auditorium – South Elevation:
- Auditorium – West Elevation:
- Finish installing flashing and trim
- Finish Installing backer rod and caulk
- Begin installing glass and pressure bar
- Begin installing insulation and horizontal cleat
- Auditorium – North Elevation:
- Finish installing backer rod and caulk
- Finish installing insulation and horizontal cleat
- Begin installing vertical siding MWC
- INTERIOR BUILD-OUT
- Rough in Framing Commons Wing
- Finish framing the auditorium fire walls and concrete furring
- Begin the MEP fire walls
- Begin framing the 2nd floor walls
- Install MEP in 2nd floor corridors
- Mechanical & Back of House:
- Install panels/feeders in electric rooms
- Continue to install all MEP in Mechanical spaces on the first floor
- Rough in Remaining First Floor:
- Finish installing MEP in walls
- Lab Wing Level 2 – Rough-in:
- Extend Down Rods
- Finish East and SW
- Finish balance of walls
- Finish the Drywall balance of wall labs
- Level 3:
- Install HM doors
- Begin MEP in labs
- Roof Level:
- Install Elevator Equipment
- Elevators:
- Stairs:
- Continue to finish stair interiors
- SITE IMPROVEMENTS
- ODFW Parking and Sidewalks:
- Finish Punch Phase one Civil
- Ramp:
- Continue to install Rock at Storm Channel
- Excavate swales and build dune