Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Continue to form and pour evacuation ramp and eyebrows
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
  • Lab High Roof West:
    • Continue installing roof
  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *
  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
    • Install flashings and window steel
  • Auditorium – North Elevation:
    • Finish installing steel studs
    • Start installing exterior gyp
  • Auditorium – East Elevation:
    • Start installing flashings, window steel, and temp window protection (if needed)
      • Auditorium – South Elevation:
    • to install window steel and flashings**
  • Auditorium – West Elevation:
    • Finish Installing weather barrier, window steel, and flashings
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding
  • Lab Wing – North Elevation:
    • Continue installing vertical siding and windows
  • Lab Wing – East Elevation:
    • Continue installing vertical siding
    • Installing windows
    • Start installing backer rod and caulk and vertical wood cladding *
  • Lab Wing – South Elevation:
    • Continue installing windows, flashings & trim, and horizontal cleat
  • Auditorium – East Elevation:
    • Finish installing windows and vertical Z girt
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical Z girt and install windows flashings and trim
  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms and place all house keeping pads.
  • Lab Wing Level 2 – Rough-in:
    • Install MEP in walls
    • Finish Stuff and spray for STC’s
  • SITE IMPROVEMENTS
  • ODF&W Parking and Sidewalks:
    • Fine grade the parking lot to be ready for asphalt
    • Excavating for Rain Garden #2 *

Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Continue to form and pour evacuation ramp and eyebrows
  • Low Roof Auditorium:
    • Continue installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Installing water barrier
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
  • Continue to install temp window protection where needed
  • Auditorium – North Elevation:
    • Finish installing steel studs
    • Start installing exterior gyp
  • Auditorium – East Elevation:
    • Start installing flashings, window steel, and temp window protection (if needed)
      • Auditorium – South Elevation:
    • Continue to install window steel and flashings**
  • Auditorium – West Elevation:
    • Installing weather barrier, window steel, and flashings

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • finish installing vertical siding
  • Lab Wing – North Elevation:
    • Continue installing vertical siding and windows

 

 

 

 

  • Lab Wing – East Elevation:
    • Continue installing vertical siding
    • Installing windows
    • Start installing backer rod and caulk and vertical wood cladding *
  • Lab Wing – South Elevation:
    • Continue installing windows, flashings & trim, and horizontal cleat
  • Auditorium – East Elevation:
    • Start installing windows and vertical Z girt
  • Auditorium – South Elevation:
    • Continue installing vertical Z girt

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Finish painting top out for MEP to start, start installing panels/feeders in electric rooms and place all house keeping pads.
  • Lab Wing Level 2 – Rough-in:
    • Install MEP in walls
    • Finish installing gyp top out one side of walls at duct locations
    • Continue tape and finish one side top out

 

  • SITE IMPROVEMENTS
  • ODF&W Parking and Sidewalks:
    • FRPS west and south curbs
    • Excavating for Rain Garden #2 *

 

Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • Low Roof Auditorium:
    • Start installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Installing water barrier
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
  • Installing window steel at head & sill, flashings, and air & water barrier
  • Auditorium – North Elevation:
    • Finish installing steel studs
    • Start installing exterior gyp
  • Auditorium – East Elevation:
    • Start installing flashings, window steel, and temp window protection (if needed)
      • Auditorium – South Elevation:
    • Continue installing air & water barrier, window steel, and flashings **
  • Auditorium – West Elevation:
    • Finish installing steel studs **
    • Start installing exterior gyp *

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Continue installing vertical wood cladding
  • Lab Wing – North Elevation:
    • Continue installing vertical wood cladding and windows

 

 

 

 

  • Lab Wing – East Elevation:
    • Finish installing horizontal cleat (pulled off to go to South side) *
    • Installing flashings and trim
    • Start installing backer rod and caulk and vertical wood cladding *
  • Lab Wing – South Elevation:
    • Continue installing windows, flashings & trim, and horizontal cleat
  • Auditorium – East Elevation:
    • Start installing windows and vertical Z girt
  • Auditorium – South Elevation:
    • Continue installing vertical Z girt

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Finish installing gyp top out & electrical rooms, tape & finish one side top out, stuffing and spraying for STC’s, sound board at OTS ceilings, and extending down rods
  • Lab Wing Level 2 – Rough-in:
    • Finish installing gyp top out one side of walls at duct locations
    • Continue installing MEP in Labs
    • Start tape and finish one side top out

 

  • SITE IMPROVEMENTS
  • Mechanical Enclosure M0101:
    • Setting Generator and ACCH-101

 

  • ODF&W Parking and Sidewalks:
    • Start installing rebar for sidewalks and mono curbs *
    • Excavating for Rain Garden #2 *

Primary construction activities for the week of 06/24 thru 06/28 will consist of the following:

|   * = Start or Finish was delayed    |   ** Start or Finish postponed   |

  • ROOFING
  • Evacuation Ramp:
    • Install expansion joint and trench drain
    • Install hot rubber roofing (moved to Lab to strip in)
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Finish installing framing *
    • Start installing sheathing *
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed)

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
  • Finish installing window steel at head & sill, flashings, air & water barrier, and temp window protection (if needed)*
    • Lab Wing – East Elevation:
  • Finish installing temp window protection (if needed) *
    • Lab Wing – South Elevation:
  • Start installing exterior gyp
  • Start installing air & water barrier, flashings, and window steel at head & sill
  • Auditorium – North Elevation:
    • Continue installing steel studs
      • Auditorium – South Elevation:
    • Installing air & water barrier, window steel, and flashings
  • Auditorium – West Elevation:
    • Installing steel studs
    • Start installing exterior gyp

 

 

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Continue installing vertical wood cladding
  • Lab Wing – North Elevation:
    • Continue installing vertical wood cladding and windows
  • Lab Wing – East Elevation:
    • Finish installing horizontal cleat
    • Installing flashings and trim
    • Start installing backer rod and caulk * and vertical wood cladding
  • Lab Wing – South Elevation:
    • Finish installing vertical Z girt
    • Continue installing windows
    • Start installing flashings and trim
  • Auditorium – South Elevation:
    • Start installing vertical Z girt

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Start stuffing and spraying for STC’s **
    • Start tape and finish one side top out
  • Lab Wing Level 2 – Rough-in:
    • Finish framing walls (starting at E/3 clockwise)
    • Continue installing MEP in Labs
    • Start installing gyp top out one side of walls at duct locations

 

  • SITE IMPROVEMENTS
  • Mechanical Enclosure M0101:
    • Finish forming sidewalks & steps and placing sidewalk and steps
  • ODF&W Parking and Sidewalks:
    • Start forming sidewalks and mono curbs *
    • Importing rock & rough grade and excavating for Rain Garden #2

 

Primary construction activities for the week of 06/17 thru 06/21 will consist of the following:

 * = Start or Finish was delayed

  • ROOFING
  • Evacuation Ramp:
    • Finish Hot rubber roofing *
    • Form and install foam at 1st 3rd of the Ramp
  • High Roof Auditorium:
    • Start installing zinc roofing
  • Low Roof Auditorium:
    • Continue installing foam into Epic deck, insulation, and cover board
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Finish installing framing *
    • Start installing sheathing *
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing air & water barrier
    • Continue installing flashing at pop outs, window steel at pop outs
    • Start installing temp window protection (if needed)

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
  • Finish installing window steel at head & sill, flashings, air & water barrier, and temp window protection (of needed)*
    • Lab Wing – North Elevation:
  • Finish installing window steel at window head & sill, flashings, and air & water barrier, and temp window protection (if needed) *
    • Lab Wing – East Elevation:
  • Finish installing window steel at window head & sill, flashings, and air & water barrier
  • Start installing temp window protection (if needed) *
    • Lab Wing – South Elevation:
  • Continue installing steel studs

 

 

  • Auditorium – North Elevation:
    • Continue installing steel studs
      • Auditorium – South Elevation:
    • Finish installing steel stud floor clips *
    • Continue installing steel studs *
  • Auditorium – West Elevation:
    • Finish installing steel stud floor clips *
  • Innovation Lab:
    • Installing window steel

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Continue installing vertical wood cladding
  • Lab Wing – North Elevation:
    • Continue installing insulation & horizontal cleat, flashings & trim, vertical wood cladding, and windows
  • Lab Wing – East Elevation:
    • Installing flashings and trim
    • Start installing backer rod and caulk
  • Lab Wing – South Elevation:
    • Start installing vertical Z girt and windows

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Finish installing in-wall MEP at Electrical Rooms *
    • Finish installing gyp top out *
    • Start stuffing and spraying for STC’s
  • Lab Wing Level 2 – Rough-in:
    • Continue installing MEP in Labs
    • Continue framing walls (starting at E/3 clockwise)

 

  • SITE IMPROVEMENTS
  • Mechanical Enclosure M0101:
    • Stripping retaining walls, damp proofing walls, back filling walls, and forming sidewalks & steps
    • Start placing sidewalk and steps at EOW
  • ODF&W Parking and Sidewalks:
    • Finish excavating for Public Rain Garden*
    • Finish balance of storm work *
    • Installing pole base and electrical for exterior light poles
    • Start forming sidewalks and mono curbs