Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- High Roof Auditorium:
- Continue to form and pour evacuation ramp and eyebrows
- Low Roof Auditorium:
- Continue installing roof
- Lab Wing Main Roof:
- Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
- Penthouses:
- Lab High Roof West:
- Continue installing roof
- FRAMING SHEATING (2nd & 3rd Floor)
- Lab Wing – South Elevation:
- Finish installing temp window protection (if needed) *
- FRAMING SHEATING (1st
Floor)
- Lab Wing – South Elevation:
- Install flashings and window steel
- Auditorium – North Elevation:
- Finish installing steel studs
- Start installing exterior gyp
- Auditorium – East Elevation:
- Start
installing flashings, window steel, and temp window protection (if needed)
- Auditorium – South Elevation:
- to install window steel and flashings**
- Start
installing flashings, window steel, and temp window protection (if needed)
- Auditorium – West Elevation:
- Finish Installing weather barrier, window steel, and flashings
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- finish installing vertical siding
- Lab Wing – North Elevation:
- Continue installing vertical siding and windows
- Lab Wing – East Elevation:
- Continue installing vertical siding
- Installing windows
- Start installing backer rod and caulk and vertical wood cladding *
- Lab Wing – South Elevation:
- Continue installing windows, flashings & trim, and horizontal cleat
- Auditorium – East Elevation:
- Finish installing windows and vertical Z girt
- Auditorium – South Elevation:
- Auditorium – West Elevation:
- Finish installing vertical Z girt and install windows flashings and trim
- INTERIOR BUILDOUT
- Mechanical & Back of House:
- Install panels/feeders in electric rooms and place all house keeping pads.
- Lab Wing Level 2 – Rough-in:
- Install MEP in walls
- Finish Stuff and spray for STC’s
- SITE IMPROVEMENTS
- ODF&W Parking and Sidewalks:
- Fine grade the parking lot to be ready for asphalt
- Excavating for Rain Garden #2 *