Primary construction activities for the week of 06/10 thru 06/14 will consist of:
- ROOFING
- High Roof Auditorium:
- Finish installing roof
- Evacuation Ramp:
- Start Hot rubber roofing *
- Low Roof Auditorium:
- Start installing foam into Epic deck
- Lab Wing Main Roof:
- Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
- Penthouses:
- Finish installing framing *
- Start installing sheathing *
- Lab High Roof West:
- Continue installing roof
- High Roof Auditorium:
- FRAMING SHEATING (2nd & 3rd Floor)
- Lab Wing – North Elevation:
- Finish installing temp window protection (if needed)
- Lab Wing – East Elevation:
- Finish installing temp window protection (if needed)
- Lab Wing – South Elevation:
- Start installing air & water barrier, window steel at pop outs, and flashing at pop outs
- Lab Wing – North Elevation:
- FRAMING SHEATING (1st Floor)
- Lab Wing – West Elevation:
- Finish installing exterior gyp board, window steel at head & sill, flashings, and air & water barrier *
- Lab Wing – North Elevation:
- Finish installing window steel at window head & sill, flashings, and air & water barrier, and temp window protection *
- Lab Wing – East Elevation:
- Finish installing exterior gyp, air & water barrier, flashings, and window steel at head & sill *
- Lab Wing – South Elevation:
- Start installing steel studs *
- Auditorium – North Elevation:
- Continue installing steel studs
- Auditorium – South Elevation:
- Finish installing steel stud floor clips *
- Continue installing steel studs *
- Auditorium – West Elevation:
- Finish installing steel stud floor clips *
- Lab Wing – West Elevation:
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- Continue installing siding horizontal cleat
- Start installing vertical siding wood cladding *
- Lab Wing – North Elevation:
- Continue installing windows
- Start installing flashings and trim
- Lab Wing – East Elevation:
- Installing windows
- Start installing vertical z girt
- Lab Wing – West Elevation:
- INTERIOR BUILDOUT
- Mechanical & Back of House:
- Finish installing in-wall MEP at Electrical Rooms
- Finish installing gyp top out
- Lab Wing Level 2 – Rough-in:
- Continue installing MEP in Labs
- Continue framing walls (starting at E/3 clockwise)
- Mechanical & Back of House:
- SITE IMPROVEMENTS
- Mechanical Enclosure M0101:
- Installing rebar, pouring, and stripping Generator Pad and footings *
- ODF&W Parking and Sidewalks:
- Finish balance of storm work *
- Installing Storm FC Manhole No.1 and storm chambers
- Excavating for Public Rain Garden
- Mechanical Enclosure M0101:
- SITEWORK & UTILITIES
- Finish installing potable water and fire water laterals
* = Start or Finish was delayed