Primary construction activities for the week of 11/04 thru 11/08 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Penthouse Framing and Sheathing:
    • Finish installing Z girts, insulation, and hat channels
    • Finish framing soffit
  • CANOPIESWest Canopy V102:Finish installing WRBStart installing frames and glass
  • Commons Wing Soffit:Finish installing hat channelStart installing trim and metal soffit panels
  • Lab Wing Soffit:Start painting vent in soffit and installing hat channel
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Start finishing siding after soffit is complete
  • Auditorium – West Elevation:
    • Installing beauty cap and flashing
  • Auditorium – North Elevation:
    • Finish installing beauty cap and flashing
  • Auditorium – East Elevation:
    • Finish siding
  • INTERIOR BUILDOUT
  • Commons Wing – Level 1 – Rough-in:
  • Installing scaffolding for MEPFP in Auditorium high ceiling *
  • Finish installing top for MEP to begin on 1st floor
  • Start installing MEPFP in Auditorium High Ceiling
  • Start installing MEP in 1st floor corridors
  • Commons Wing – Level 2 – Designs 3D & Art Studio:
    • Finishing drywall *
    • Painting
  • Commons Wing – Level 2 – Sound Control and Vestibules:
    • Finish installing MEP at hard lids
    • Installing gyp at lids and walls (contingent on passing hard lid inspection)
    • Start finishing lids and walls
  • Lab Wing – Level 1 – Rough-in:
  • Start installing overhead MEP work in OTS
  • Lab Wing –  Level 2 – Rough-in:
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 2 – Offices and Conference Rooms:
    • Start finishing MEP in grid
  • Lab Wing –  Level 2 – Bathrooms and Hard Lid Rooms
    • Installing gyp at lids and walls
    • Start finishing gyp
  • Lab Wing –  Level 3 Rough-in:
    • Finish installing MEP in Labs overhead
    • Finish framing walls at E/3 then clockwise
    • Finish installing MEP in walls at Doughnut
    • Start topping out gyp at Doughnut
  • Roof – West Penthouse ELEV Equip Room:
  • Installing disconnects
  • Start installing elevator equipment
  • Elevator 2:
    • Start installing elevator
Print Friendly, PDF & Email

Leave a reply