Primary construction activities for the week of 10/28 thru 11/01 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- High Roof Auditorium:
- Penthouse Framing and Sheathing:
- Continue Z girts, insulation, and hat channels
- Start framing soffit
- CANOPIESEast Canopy V103:Installing frames and glass
- South Canopy V101:Installing frames and glass
- West Canopy V102:Finish framingInstalling electrical, and gyping the lidStart installing WRBCommons Wing Soffit:Painting vent in soffitStart installing hat channelLab Wing Soffit:Installing soffit WRB
- WINDOWS & SIDING
- Auditorium – South Elevation:
- Finish installing glass, pressure bar, and vertical siding MWC
- Auditorium – West Elevation:
- Finish installing glass, pressure bar, and siding
- Auditorium – North Elevation:
- Finish installing glass and pressure bar
- Siding in Armpit delayed for concrete to finish
- Start installing beauty cap and flashing
- Auditorium – East Elevation:
- Finish siding, beauty cap, and flashing – delayed for concrete work to finish
- INTERIOR BUILDOUT
- Commons Wing – Level 1 – Rough-in:
- Finish MEP in walls on 1st floor
- Installing scaffolding for MEPFP in Auditorium high ceiling
- Start installing top for MEP to begin on 1st floor
- Commons Wing – Level 2 – Designs 3D
& Art Studio:
- Polishing floors
- Finishing drywall
- Commons Wing – Level 2 – Sound Control
and Vestibules:
- Framing hard lids
- Start installing MEP at hard lids
- Lab Wing – Level 1 – Rough-in:
- Finish installing OTS insulation
- Painting top out and OTS
- Lab Wing – Level 2 – Rough-in:
- Continue installing cable tray at OTS and Commons
- Lab
Wing – Level 2 – Offices and Conference Rooms:
- Installing grid *
- Lab
Wing – Level 2 – Bathrooms and Hard Lid Rooms
- Finish installing MEP at hard lids *
- MEP inspection for hard lids
- Lab Wing – Level 3 Rough-in:
- Continue installing MEP in Labs overhead
- Continue framing walls at E/3 then clockwise
- Installing MEP in walls at Doughnut
- Roof – West Penthouse ELEV Equip Room:
- Finishing shaft framing, gyp, and finish