Primary construction activities for the week of 10/14 thru 10/18 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab Wing Main Roof:
    • Start installing insulation
  • Lab High Roof West:
    • Start installing roofing
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Finish installing windows and vertical siding MWC
  • Auditorium – West Elevation:
    • Finish installing windows*
    • Installing vertical siding MWC
  • Auditorium – North Elevation:
    • Finish installing beauty cap and flashing
    • Installing vertical siding MWC
  • Auditorium – East Elevation:
    • Finish installing beauty cap and flashing
    • Continue installing vertical siding MWC
  • INTERIOR BUILDOUT
  • Mechanical Back of House:
    • Finish installing all MEP in mechanical spaces 1st floor
  • Commons Wing – Rough-in Framing:
  • Finish MEP in Walls on 2nd floor
  • Framing bathroom shear walls and walls
  • Start installing MEP at 2nd floor corridors
  • Lab Wing – Level 1 Rough-in Remaining:
  • Finish installing OTS insulation
  • Painting top out and OTS
  • Lab Wing –  Level 2 Rough-in:
    • Finish installing Electrical in OTS Commons
    • Continue installing cable tray at OTS and Commons
  • Lab Wing – Level 2 – Offices and Conference Rooms
    • Start installing MEP at ceilings
  • Lab Wing – Level 2 – Labs:
    • Installing grid and necessary tiles
  • Lab Wing – Level 2 – Bathrooms and Hard Lid Rooms
    • Start framing hard lids
    • Start installing MEP at hard lids.
  • Lab Wing –  Level 3 Rough-in:
    • Start installing MEP in Labs overhead
    • Start framing walls at E/3 then clockwise
  • Roof – West Penthouse ELEV Equip Room:
  • Installing elevator equipment
  • Start installing fire protection
  • Roof – East Penthouse Storage, ELEV Lobby, & Staging:
  • Installing Gyp *
  • Start finishing Gyp *
  • SITE IMPROVEMENTS
  • Courtyard:
    • Pour 5 Heavy (FRPS) (Form, Rebar, Pour, Strip (FRPS))*
    • Pour 6 Heavy (FRPS) *
    • Start placing rock for East sidewalk
Print Friendly, PDF & Email

Leave a reply