Primary construction activities for the week of 10/14 thru 10/18 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- High Roof Auditorium:
- Lab Wing Main Roof:
- Start installing insulation
- Lab High Roof West:
- Start installing roofing
- WINDOWS & SIDING
- Auditorium – South Elevation:
- Finish installing windows and vertical siding MWC
- Auditorium – West Elevation:
- Finish installing windows*
- Installing vertical siding MWC
- Auditorium – North Elevation:
- Finish installing beauty cap and flashing
- Installing vertical siding MWC
- Auditorium – East Elevation:
- Finish installing beauty cap and flashing
- Continue installing vertical siding MWC
- INTERIOR BUILDOUT
- Mechanical Back of House:
- Finish installing all MEP in mechanical spaces 1st floor
- Commons Wing – Rough-in Framing:
- Finish MEP in Walls on 2nd floor
- Framing bathroom shear walls and walls
- Start installing MEP at 2nd floor corridors
- Lab Wing – Level 1 Rough-in Remaining:
- Finish installing OTS insulation
- Painting top out and OTS
- Lab Wing – Level 2 Rough-in:
- Finish installing Electrical in OTS Commons
- Continue installing cable tray at OTS and Commons
- Lab Wing – Level 2 – Offices and
Conference Rooms
- Start installing MEP at ceilings
- Lab Wing – Level 2 – Labs:
- Installing grid and necessary tiles
- Lab Wing – Level 2 – Bathrooms and
Hard Lid Rooms
- Start framing hard lids
- Start installing MEP at hard lids.
- Lab Wing – Level 3 Rough-in:
- Start installing MEP in Labs overhead
- Start framing walls at E/3 then clockwise
- Roof – West Penthouse ELEV Equip Room:
- Installing elevator equipment
- Start installing fire protection
- Roof – East Penthouse Storage, ELEV Lobby, & Staging:
- Installing Gyp *
- Start finishing Gyp *
- SITE IMPROVEMENTS
- Courtyard:
- Pour 5 Heavy (FRPS) (Form, Rebar, Pour, Strip (FRPS))*
- Pour 6 Heavy (FRPS) *
- Start placing rock for East sidewalk