Primary construction activities for the week of 10/07 thru 10/11 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- High Roof Auditorium:
- Lab Wing Main Roof:
- All topping poured. Start installing Z Girt next week.
- WINDOWS & SIDING
- Auditorium – South Elevation:
- Start installing windows
- Auditorium – West Elevation:
- Finish installing windows
- Start installing backer rod and caulk
- Auditorium – North Elevation:
- Finish installing beauty cap and flashing
- Installing vertical siding MWC
- INTERIOR BUILDOUT
- Commons Wing – Rough-in Framing:
- Finish MEP above and below Mezz decking
- Start framing 1st floor walls
- Start MEP in Walls on 2nd floor *
- Lab Wing – Level 1 Rough-in Remaining:
- Finish stuff and spray at head of walls
- Installing OTS insulation
- Lab Wing – Level 2 Rough-in:
- Finish
installing Duct Work in OTS Commons and Offices
- Continue installing Electrical in OTS Commons
- Continue installing cable tray at OTS and Commons
- Lab Wing – Level 3 Rough-in:
- Start laying out walls and wall penetrations
- Roof – West Penthouse ELEV Equip Room:
- Continue installing Fire Protection *
- Roof – East Penthouse Storage, ELEV Lobby, & Staging:
- Installing Gyp *
- Start finishing Gyp *
- SITE IMPROVEMENTS
- Courtyard:
- Finishing Pour 4 (Form, Rebar, Pour, Strip (FRPS))
- Finishing Pour 5 Heavy (FRPS)
- Finishing Pour 6 Heavy (FRPS)