Primary construction activities for the week of 10/07 thru 10/11 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab Wing Main Roof:
    • All topping poured. Start installing Z Girt next week.
  • WINDOWS & SIDING
  • Auditorium – South Elevation:
    • Start installing windows
  • Auditorium – West Elevation:
    • Finish installing windows
    • Start installing backer rod and caulk
  • Auditorium – North Elevation:
    • Finish installing beauty cap and flashing
    • Installing vertical siding MWC
  • INTERIOR BUILDOUT
  • Commons Wing – Rough-in Framing:
  • Finish MEP above and below Mezz decking
  • Start framing 1st floor walls
  • Start MEP in Walls on 2nd floor *
  • Lab Wing – Level 1 Rough-in Remaining:
  • Finish stuff and spray at head of walls
  • Installing OTS insulation
  • Lab Wing –  Level 2 Rough-in:
  • Finish installing Duct Work in OTS Commons and Offices
    • Continue installing Electrical in OTS Commons
    • Continue installing cable tray at OTS and Commons
  • Lab Wing –  Level 3 Rough-in:
    • Start laying out walls and wall penetrations
  • Roof – West Penthouse ELEV Equip Room:
  • Continue installing Fire Protection *
  • Roof – East Penthouse Storage, ELEV Lobby, & Staging:
  • Installing Gyp *
  • Start finishing Gyp *
  • SITE IMPROVEMENTS
  • Courtyard:
    • Finishing Pour 4 (Form, Rebar, Pour, Strip (FRPS))
    • Finishing Pour 5 Heavy (FRPS)
    • Finishing Pour 6 Heavy (FRPS)