Primary construction activities for the week of 09/30 thru 10/5 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- High Roof Auditorium:
- Lab Wing Main Roof:
- Rebar installed, pouring next week
- WINDOWS & SIDING
- Lab Wing – North Elevation:
- Lab Wing – South Elevation:
- Auditorium – East Elevation:
- Auditorium – South Elevation:
- Auditorium – West Elevation:
- Finish installing vertical siding MWC
- Install glass and pressure bar
- Install beauty cap and flashing
- Auditorium – North Elevation:
- Start installing glass and pressure bar *
- Start installing insulation and horizontal cleat
- Install glass and pressure bar
- Install beauty cap and flashing
- INTERIOR BUILDOUT
- Commons Wing – Rough-in Framing:
- MEP in Walls on 2nd floor *
- Start installing upper seating framing
- Install bathroom carriers
- Frame first floors
- MEP above and below Mezz decking
- Mechanical & Back of House:
- Continue to install all MEP in Mechanical spaces on the 1st floor
- Lab Wing – Rough in Remaining First Floor:
- Finish installing Top Out
- Start top out finish *
- Lab Wing – Level 2 Rough-in:
- to install Hydronic piping in OTS Commons
- Fire Protection in OTS commons
- Continue to install Electrical in OTS Commons
- Continue to install Plumbing in OTS Commons
- Continue to install Duct Work in OTS Commons and Offices
- Finishing all paint on 2nd floor *
- Roof – West Penthouse ELEV Equip Room:
- Installing Fire Protection *
- Install cover for MEP
- Roof – East Penthouse Stor, ELEV Lobby & Staging:
- Install Gyp *
- Start finishing Gyp *
- Install ceiling ots insulation
- Start painting room
- SITE IMPROVEMENTS
- Ramp:
- Courtyard:
- Finish grade
- Begin pours