Primary construction activities for the week of 09/30 thru 10/5 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab Wing Main Roof:
    • Rebar installed, pouring next week
  • WINDOWS & SIDING
  • Lab Wing – North Elevation:
  • Lab Wing – South Elevation:
  • Auditorium – East Elevation:
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish installing vertical siding MWC
    • Install glass and pressure bar
    • Install beauty cap and flashing
  • Auditorium – North Elevation:
    • Start installing glass and pressure bar *
    • Start installing insulation and horizontal cleat
    • Install glass and pressure bar
    • Install beauty cap and flashing
  • INTERIOR BUILDOUT
  • Commons Wing – Rough-in Framing:
  • MEP in Walls on 2nd floor *
  • Start installing upper seating framing
  • Install bathroom carriers
  • Frame first floors
  • MEP above and below  Mezz decking
  • Mechanical & Back of House:
    • Continue to install all MEP in Mechanical spaces on the 1st floor
  • Lab Wing – Rough in Remaining First Floor:
  • Finish installing Top Out
  • Start top out finish *
  • Lab Wing –  Level 2 Rough-in:
    • to install Hydronic piping in OTS Commons
    • Fire Protection in OTS commons
    • Continue to install Electrical in OTS Commons
    • Continue to install Plumbing in OTS Commons
    • Continue to install Duct Work in OTS Commons and Offices
    • Finishing all paint on 2nd floor *
  • Roof – West Penthouse ELEV Equip Room:
  • Installing Fire Protection *
  • Install cover for MEP
  • Roof – East Penthouse Stor, ELEV Lobby & Staging:
  • Install Gyp *
  • Start finishing Gyp *
  • Install ceiling ots insulation
  • Start painting room
  • SITE IMPROVEMENTS
  • Ramp:
  • Courtyard:
    • Finish grade
    • Begin pours