Primary construction activities for the week of 09/23 thru 09/27 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Lab Wing Main Roof:
    • Rebar installed, pouring next week
  • WINDOWS & SIDING
  • Lab Wing – North Elevation:
  • Continue installing Curtain Wall Center
  • Lab Wing – South Elevation:
    • Finishing installing MWC *
  • Auditorium – East Elevation:
    • Finish installing vertical siding MWC
    • Installing beauty cap and flashing
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
  • Finish installing vertical siding MWC
  • Auditorium – North Elevation:
    • Installing flashings and trim
    • Installing backer rod and caulk *
    • Start installing glass and pressure bar *
    • Start installing insulation and horizontal cleat
  • INTERIOR BUILDOUT
  • Commons Wing – Rough-in Framing:
  • Finish installing MEP and fire Protection in auditorium high ceiling
  • Start MEP in Walls on 2nd floor *
  • Finish installing MEP in Soffit and wall above
  • Start installing bathroom carriers *
  • Start installing metal decking and  replace beams
  • Start building soffit hard lid, duct, beam, and walls
  • Start installing upper seating framing
  • Mechanical & Back of House:
    • Finish installing panels/feeders in electric rooms
    • Continue to install all MEP in Mechanical spaces on the 1st floor
  • Lab Wing – Rough in Remaining First Floor:
  • Finish installing Top Out
  • Start top out finish *
  • Lab Wing –  Level 2 Rough-in:
    • to install Hydronic piping in OTS Commons
    • Fire Protection in OTS commons
    • Continue to install Electrical in OTS Commons
    • Continue to install Plumbing in OTS Commons
    • Continue to install Duct Work in OTS Commons and Offices
    • Finishing all paint on 2nd floor *
  • Roof – West Penthouse ELEV Equip Room:
  • Finish installing Elevator equipment *
  • Installing Fire Protection *
  • Roof – East Penthouse Stor, ELEV Lobby & Staging:
  • Install Gyp *
  • Start finishing Gyp *
  • SITE IMPROVEMENTS
  • Ramp:
    • Install rebar
    • Placing 2nd half of Ramp slab
    • Begin Pouring ramp slab
    • Start installing trench drain
  • Courtyard:
    • Installing Storm and Electrical
    • Start cutting to grade
Print Friendly, PDF & Email

Leave a reply