Primary construction activities for the week of 09/23 thru 09/27 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- High Roof Auditorium:
- Lab Wing Main Roof:
- Rebar installed, pouring next week
- WINDOWS & SIDING
- Lab Wing – North Elevation:
- Continue installing Curtain Wall Center
- Lab Wing – South Elevation:
- Finishing installing MWC *
- Auditorium – East Elevation:
- Finish installing vertical siding MWC
- Installing beauty cap and flashing
- Auditorium – South Elevation:
- Auditorium – West Elevation:
- Finish installing vertical siding MWC
- Auditorium – North Elevation:
- Installing flashings and trim
- Installing backer rod and caulk *
- Start installing glass and pressure bar *
- Start installing insulation and horizontal cleat
- INTERIOR BUILDOUT
- Commons Wing – Rough-in Framing:
- Finish installing MEP and fire Protection in auditorium high ceiling
- Start MEP in Walls on 2nd floor *
- Finish installing MEP in Soffit and wall above
- Start installing bathroom carriers *
- Start installing metal decking and replace beams
- Start building soffit hard lid, duct, beam, and walls
- Start installing upper seating framing
- Mechanical & Back of House:
- Finish installing panels/feeders in electric rooms
- Continue to install all MEP in Mechanical spaces on the 1st floor
- Lab Wing – Rough in Remaining First Floor:
- Finish installing Top Out
- Start top out finish *
- Lab Wing – Level 2 Rough-in:
- to install Hydronic piping in OTS Commons
- Fire Protection in OTS commons
- Continue to install Electrical in OTS Commons
- Continue to install Plumbing in OTS Commons
- Continue to install Duct Work in OTS Commons and Offices
- Finishing all paint on 2nd floor *
- Roof – West Penthouse ELEV Equip Room:
- Finish installing Elevator equipment *
- Installing Fire Protection *
- Roof – East Penthouse Stor, ELEV Lobby & Staging:
- Install Gyp *
- Start finishing Gyp *
- SITE IMPROVEMENTS
- Ramp:
- Install rebar
- Placing 2nd half of Ramp slab
- Begin Pouring ramp slab
- Start installing trench drain
- Courtyard:
- Installing Storm and Electrical
- Start cutting to grade