Primary construction activities for the week of 09/16 thru 09/20 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- High Roof Auditorium:
- Low Roof Auditorium:
- Finish installing siding
- Begin Installing Zinc Roofing
- Lab Wing Main Roof:
- Continue to install the exterior concrete topping slabs
- Penthouses:
- Lab High Roof West:
- FRAMING SHEATING
- – South Elevation:
- Commons Wing – North Elevation:
- Commons Wing – East Elevation:
- Commons Wing – West Elevation:
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- Lab Wing – North Elevation:
- Install Curtain Wall Center
- Lab Wing – East Elevation:
- Lab Wing – South Elevation:
- Auditorium – East Elevation:
- Finish installing windows
- Begin Backer rod and caulk
- Auditorium – South Elevation:
- Auditorium – West Elevation:
- Continue installing vertical siding MWC
- Auditorium – North Elevation:
- Finish installing windows
- Backer rod and caulk
- Begin installing glass and pressure bar
- Install flashing and trim
- INTERIOR BUILD-OUT
- Rough in Framing Commons Wing
- Begin build soffit and wall above and below
- Begin to install top out for MEP to start 2nd floor
- Begin installing MEP and fire Protection in auditorium high ceiling
- Begin MEP in Walls on 2nd floor
- MEP soffit and wall above
- Install Bathroom carriers
- Begin to install bathroom carriers
- Mechanical & Back of House:
- Install panels/feeders in electric rooms
- Continue to install all MEP in Mechanical spaces on the first floor
- Rough in Remaining First Floor:
- Install Top Out
- Begin top out finish
- Lab Wing Level 2 – Rough-in:
- to install hydronic piping in OTS Commons
- fire protection in OTS commons
- Continue to install electrical in OTS Commons
- Continue to install Plumbing in OTS Commons
- Continue to install Duct Work in OTS Commons
- Finish all paint on 2nd floor
- Level 3:
- Roof Level:
- Finish MEP in walls
- Finish installing Elevator equipment
- Begin Installing fire protection
- Install Gyp
- Finish Gyp
- Elevators:
- Stairs:
- SITE IMPROVEMENTS
- ODFW Parking and Sidewalks:
- Ramp:
- Install edge form and rebar
- Begin Pouring ramp slab
- Install storm channel and electrical
- Begin cutting to grade