Primary construction activities for the week of 09/01 thru 09/05 will consist of the following:  

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • High Roof Auditorium:
  • Low Roof Auditorium:
    • Continue installing siding
  • Lab Wing Main Roof:
    • Continue to install the exterior concrete topping slabs
  • Penthouses:
  • Lab High Roof West:
  • FRAMING SHEATING
    • – South Elevation:
  • Commons Wing – North Elevation:
  • Commons Wing – East Elevation:
  • Commons Wing – West Elevation:
  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
  • Lab Wing – North Elevation:
  • Lab Wing – East Elevation:
  • Lab Wing – South Elevation:
    • Finish installing vertical siding MWC
  • Auditorium – East Elevation:
    • Install beauty cap and flashing
  • Auditorium – South Elevation:
  • Auditorium – West Elevation:
    • Finish  installing glass and pressure bar
    • Finish installing insulation and horizontal cleat
    • Begin installing beauty cap and flashing
    • Begin installing vertical siding MWC
  • Auditorium – North Elevation:
    • Install beauty cap and flashing
    • Finish installing vertical siding MWC
  • INTERIOR BUILD OUT
  • Rough in Framing Commons Wing
  • Finish the MEP fire walls
  • Install balance drywall 2nd floor walls
  • Mechanical & Back of House:
    • Install panels/feeders in electric rooms
    • Continue to install all MEP in Mechanical spaces on the first floor
  • Rough in Remaining First Floor:
  • Finish installing MEP in walls
  • Lab Wing Level 2 – Rough-in:
    • fire protection in OTS commons
    • Begin to install electrical in OTS Commons
    • Begin to install Plumbing in OTS Commons
    • Begin to install Duct Work in OTS Commons
    • Begin to paint East and Southwest
    • Begin to finish balance of walls
  • Level 3:
  • Continue MEP in labs
  • Roof Level:
  • Install fire protection and cover for MEP
  • Begin MEP in walls
  • Elevators:
  • Stairs:
    • Continue to finish stair interiors
  • SITE IMPROVEMENTS
  • ODFW Parking and Sidewalks:
  • Ramp:
    • Continue to install Rock at Storm Channel
    • Cut to grade
Print Friendly, PDF & Email

Leave a reply