Primary construction activities for the week of 09/01 thru 09/05 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- High Roof Auditorium:
- Low Roof Auditorium:
- Continue installing siding
- Lab Wing Main Roof:
- Continue to install the exterior concrete topping slabs
- Penthouses:
- Lab High Roof West:
- FRAMING SHEATING
- – South Elevation:
- Commons Wing – North Elevation:
- Commons Wing – East Elevation:
- Commons Wing – West Elevation:
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- Lab Wing – North Elevation:
- Lab Wing – East Elevation:
- Lab Wing – South Elevation:
- Finish installing vertical siding MWC
- Auditorium – East Elevation:
- Install beauty cap and flashing
- Auditorium – South Elevation:
- Auditorium – West Elevation:
- Finish installing glass and pressure bar
- Finish installing insulation and horizontal cleat
- Begin installing beauty cap and flashing
- Begin installing vertical siding MWC
- Auditorium – North Elevation:
- Install beauty cap and flashing
- Finish installing vertical siding MWC
- INTERIOR BUILD OUT
- Rough in Framing Commons Wing
- Finish the MEP fire walls
- Install balance drywall 2nd floor walls
- Mechanical & Back of House:
- Install panels/feeders in electric rooms
- Continue to install all MEP in Mechanical spaces on the first floor
- Rough in Remaining First Floor:
- Finish installing MEP in walls
- Lab Wing Level 2 – Rough-in:
- fire protection in OTS commons
- Begin to install electrical in OTS Commons
- Begin to install Plumbing in OTS Commons
- Begin to install Duct Work in OTS Commons
- Begin to paint East and Southwest
- Begin to finish balance of walls
- Level 3:
- Continue MEP in labs
- Roof Level:
- Install fire protection and cover for MEP
- Begin MEP in walls
- Elevators:
- Stairs:
- Continue to finish stair interiors
- SITE IMPROVEMENTS
- ODFW Parking and Sidewalks:
- Ramp:
- Continue to install Rock at Storm Channel
- Cut to grade