Primary construction activities for the week of 08/19 thru 08/23 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- High Roof Auditorium:
- Low Roof Auditorium:
- Finish installing furring
- Install windows
- Lab Wing Main Roof:
- Continue installing drain mat foam and rock ballast\
- Set AHU-401 & EF401 and 402
- Penthouses:
- Lab High Roof West:
- FRAMING SHEATING
- – South Elevation:
- Finish installing window steel
- Commons Wing – North Elevation:
- Finish installing temp window protection (if needed) *
- Commons Wing – East Elevation:
- Commons Wing – West Elevation:
- Finish installing temp window protection if needed
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- Lab Wing – North Elevation:
- Finish installing vertical siding MWC
- Begin installing beauty cap and flashing
- Lab Wing – East Elevation:
- Lab Wing – South Elevation:
- Begin installing horizontal cleat
- Finish Installing beauty cap and flashing
- Auditorium – East Elevation:
- Finish installing windows
- Install flashings and trim
- Install backer rod and caulk
- Begin installing insulation and horizontal cleat
- Auditorium – South Elevation:
- Auditorium – West Elevation:
- Finish installing vertical Z girt and install windows
- Begin installing flashing and trim
- Begin backer rod and caulk
- Auditorium – North Elevation:
- Finish Installing windows
- Begin to install flashing and trim
- Install backer rod and caulk
- Begin installing insulation and horizontal cleat
- INTERIOR BUILD-OUT
- Rough in Framing Commons Wing
- Begin to frame the auditorium fire walls and concrete furring
- Finish the MEP walls on the 2nd floor
- Mechanical & Back of House:
- Install panels/feeders in electric rooms
- Continue to install all MEP in Mechanical spaces on the first floor
- Rough in Remaining First Floor:
- Begin installing MEP in walls
- Lab Wing Level 2 – Rough-in:
- Install sound board at OTS Ceilings Donut
- Paint Top out for MEP to start Donut
- Finish East and SW
- Finish the Complete balance of MEP in the walls
- Begin the Drywall balance of wall labs
- Roof Level:
- Finish Painting Room
- Install the Disconnects
- Begin Installing Elevator equipment
- Elevators:
- Stairs:
- Continue to finish stair interiors
- SITE IMPROVEMENTS
- ODFW Parking and Sidewalks:
- Install signs and stripe
- Begin Punch Phase one Civil
- Ramp:
- Finish back-filling up to Elevation
- Begin to install Rock at Storm Channel