Primary construction activities for the week of 08/12 thru 08/16 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- High Roof Auditorium:
- Low Roof Auditorium:
- Continue framing and sheeting at truss
- Finish installing green gert and foam
- Install furring
- Begin installing window
- Lab Wing Main Roof:
- Conduct water test
- Begin installing drain matt foam and rock ballast
- Penthouses:
- Lab High Roof West:
- FRAMING SHEATING
- – South Elevation:
- Finish installing window steel
- Commons Wing – North Elevation:
- Finish installing temp window protection (if needed) *
- Commons Wing – East Elevation:
- Commons Wing – West Elevation:
- Finish installing temp window protection if needed
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- Finish installing vertical siding MWC
- Lab Wing – North Elevation:
- Finish installing vertical siding MWC
- Begin installing beauty cap and flashing
- Lab Wing – East Elevation:
- Lab Wing – South Elevation:
- Begin installing horizontal cleat
- Finish Installing beauty cap and flashing
- Auditorium – East Elevation:
- Finish installing windows
- Install flashings and trim
- Install backer rod and caulk
- Begin installing insulation and horizontal cleat
- Auditorium – South Elevation:
- Auditorium – West Elevation:
- Finish installing vertical Z girt and install windows
- Begin installing flashings and trim
- Begin backer rod and caulk
- Auditorium – North Elevation:
- Finish installing vertical Z girt
- Finish Installing windows
- Begin to install flashings and trim
- Install backer rod and caulk
- INTERIOR BUILDOUT
- Rough in Framing Commons Wing
- Begin to frame auditorium fire walls and concrete furring
- Mechanical & Back of House:
- Install panels/feeders in electric rooms
- Continue to install all MEP in Mechanical spaces on the first floor
- Rough in Remaining First Floor:
- Finishing Framing
- QC all MEP openings in the walls
- Begin installing MEP in walls
- Lab Wing Level 2 – Rough-in:
- Finish complete balance of MEP in walls
- Install drywall on the East and Southwest
- Stuff and Spray STC’s Donut
- Roof Level:
- Install Gyp
- Stuff and Spray Top of Wall
- Install Ceiling OTS Insulation
- Begin to Paint Room
- Elevators:
- Procure Elevator
- Stairs:
- Continue to finish stair interiors
- SITE IMPROVEMENTS
- ODF&W Parking and Sidewalks:
- Install Irrigation
- Finish Final Grade West and North around swales
- Begin Installing top soil
- Begin Installing light Poles
- Ramp:
- Finish backfilling up to -42”
- Install temporary handrail posts and railing
- Begin backfilling to elevation