Primary construction activities for the week of 07/29 thru 08/02 will consist of the following:
| * = Start or Finish was delayed | ** Activity taking longer than projected |
- ROOFING
- High Roof Auditorium:
- Continue to form and pour evacuation ramp and eyebrows
- Low Roof Auditorium:
- Continue installing roof
- Lab Wing Main Roof:
- Continue installing hot fluid-applied rubber asphalt
- Penthouses:
- Lab High Roof West:
- Continue installing roof
- FRAMING SHEATING (2nd & 3rd Floor)
- Lab Wing – South Elevation:
- Finish installing temp window protection (if needed) *
- FRAMING SHEATING (1st
Floor)
- Lab Wing – South Elevation:
- Finish installing flashings and window steel
- Auditorium – North Elevation:
- Finish installing exterior gyp
- Start installation of window steel as well as the air and water barrier
- Install the flashings
- Auditorium – East Elevation:Auditorium – South Elevation:
- to install window steel and flashings**
- Auditorium – West Elevation:
- Finish Installing weather barrier, window steel, and flashings
- Begin installing temp window protection if needed
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- finish installing vertical siding
- Lab Wing – North Elevation:
- Continue installing vertical siding
- Begin installing beauty cap and flashing
- Lab Wing – East Elevation:
- Install beauty cap and flashing
- Lab Wing – South Elevation:
- Finish installing beauty cap and flashing
- Begin installing horizontal cleat
- Auditorium – East Elevation:
- Install flashings and trim
- Install backer rod and caulk
- Begin installing insulation and horizontal cleat
- Auditorium – South Elevation:
- Auditorium – West Elevation:
- Finish installing vertical Z girt and install windows, flashings and trim
- Auditorium – North Elevation:
- Begin installing vertical Z girt
- INTERIOR BUILDOUT
- Mechanical & Back of House:
- Install panels/feeders in electric rooms
- Lab Wing Level 2 – Rough-in:
- Finish Stuff and spray for STC’s
- Stairs:
- Continue to finish stair interiors
- SITE IMPROVEMENTS
- ODF&W Parking and Sidewalks:
- Remove asphalt and fine grade East side
- Ramp:
- Finish backfilling up to the fluid applied weather protection
- Begin the complete bentonite and fluid applied weather protection