Primary construction activities for the week of 07/01 thru 07/05 will consist of the following:

|   * = Start or Finish was delayed    |   ** Activity taking longer than projected   |

  • ROOFING
  • Low Roof Auditorium:
    • Start installing roof
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Installing water barrier
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing temp window protection (if needed) *

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – South Elevation:
  • Installing window steel at head & sill, flashings, and air & water barrier
  • Auditorium – North Elevation:
    • Finish installing steel studs
    • Start installing exterior gyp
  • Auditorium – East Elevation:
    • Start installing flashings, window steel, and temp window protection (if needed)
      • Auditorium – South Elevation:
    • Continue installing air & water barrier, window steel, and flashings **
  • Auditorium – West Elevation:
    • Finish installing steel studs **
    • Start installing exterior gyp *

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Continue installing vertical wood cladding
  • Lab Wing – North Elevation:
    • Continue installing vertical wood cladding and windows

 

 

 

 

  • Lab Wing – East Elevation:
    • Finish installing horizontal cleat (pulled off to go to South side) *
    • Installing flashings and trim
    • Start installing backer rod and caulk and vertical wood cladding *
  • Lab Wing – South Elevation:
    • Continue installing windows, flashings & trim, and horizontal cleat
  • Auditorium – East Elevation:
    • Start installing windows and vertical Z girt
  • Auditorium – South Elevation:
    • Continue installing vertical Z girt

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Finish installing gyp top out & electrical rooms, tape & finish one side top out, stuffing and spraying for STC’s, sound board at OTS ceilings, and extending down rods
  • Lab Wing Level 2 – Rough-in:
    • Finish installing gyp top out one side of walls at duct locations
    • Continue installing MEP in Labs
    • Start tape and finish one side top out

 

  • SITE IMPROVEMENTS
  • Mechanical Enclosure M0101:
    • Setting Generator and ACCH-101

 

  • ODF&W Parking and Sidewalks:
    • Start installing rebar for sidewalks and mono curbs *
    • Excavating for Rain Garden #2 *