Primary construction activities for the week of 06/24 thru 06/28 will consist of the following:
| * = Start or Finish was delayed | ** Start or Finish postponed |
- ROOFING
- Evacuation Ramp:
- Install expansion joint and trench drain
- Install hot rubber roofing (moved to Lab to strip in)
- Lab Wing Main Roof:
- Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
- Penthouses:
- Finish installing framing *
- Start installing sheathing *
- Lab High Roof West:
- Continue installing roof
- FRAMING SHEATING (2nd & 3rd Floor)
- Lab Wing – South Elevation:
- Finish installing temp window protection (if needed)
- FRAMING SHEATING (1st Floor)
- Lab Wing – West Elevation:
- Finish installing window steel at head & sill, flashings, air & water barrier, and temp window protection (if needed)*
- Lab Wing – East Elevation:
- Finish installing temp window protection (if needed) *
- Lab Wing – South Elevation:
- Start installing exterior gyp
- Start installing air & water barrier, flashings, and window steel at head & sill
- Auditorium – North Elevation:
- Continue installing steel studs
- Auditorium – South Elevation:
- Installing air & water barrier, window steel, and flashings
- Continue installing steel studs
- Auditorium – West Elevation:
- Installing steel studs
- Start installing exterior gyp
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- Continue installing vertical wood cladding
- Lab Wing – North Elevation:
- Continue installing vertical wood cladding and windows
- Lab Wing – East Elevation:
- Finish installing horizontal cleat
- Installing flashings and trim
- Start installing backer rod and caulk * and vertical wood cladding
- Lab Wing – South Elevation:
- Finish installing vertical Z girt
- Continue installing windows
- Start installing flashings and trim
- Auditorium – South Elevation:
- Start installing vertical Z girt
- INTERIOR BUILDOUT
- Mechanical & Back of House:
- Start stuffing and spraying for STC’s **
- Start tape and finish one side top out
- Lab Wing Level 2 – Rough-in:
- Finish framing walls (starting at E/3 clockwise)
- Continue installing MEP in Labs
- Start installing gyp top out one side of walls at duct locations
- SITE IMPROVEMENTS
- Mechanical Enclosure M0101:
- Finish forming sidewalks & steps and placing sidewalk and steps
- ODF&W Parking and Sidewalks:
- Start forming sidewalks and mono curbs *
- Importing rock & rough grade and excavating for Rain Garden #2