Primary construction activities for the week of 06/17 thru 06/21 will consist of the following:
* = Start or Finish was delayed
- ROOFING
- Evacuation Ramp:
- Finish Hot rubber roofing *
- Form and install foam at 1st 3rd of the Ramp
- High Roof Auditorium:
- Start installing zinc roofing
- Low Roof Auditorium:
- Continue installing foam into Epic deck, insulation, and cover board
- Lab Wing Main Roof:
- Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
- Penthouses:
- Finish installing framing *
- Start installing sheathing *
- Lab High Roof West:
- Continue installing roof
- FRAMING SHEATING (2nd & 3rd Floor)
- Lab Wing – South Elevation:
- Finish installing air & water barrier
- Continue installing flashing at pop outs, window steel at pop outs
- Start installing temp window protection (if needed)
- FRAMING SHEATING (1st Floor)
- Lab Wing – West Elevation:
- Finish installing window steel at head & sill, flashings, air & water barrier, and temp window protection (of needed)*
- Lab Wing – North Elevation:
- Finish installing window steel at window head & sill, flashings, and air & water barrier, and temp window protection (if needed) *
- Lab Wing – East Elevation:
- Finish installing window steel at window head & sill, flashings, and air & water barrier
- Start installing temp window protection (if needed) *
- Lab Wing – South Elevation:
- Continue installing steel studs
- Auditorium – North Elevation:
- Continue installing steel studs
- Auditorium – South Elevation:
- Finish installing steel stud floor clips *
- Continue installing steel studs *
- Continue installing steel studs
- Auditorium – West Elevation:
- Finish installing steel stud floor clips *
- Innovation Lab:
- Installing window steel
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- Continue installing vertical wood cladding
- Lab Wing – North Elevation:
- Continue installing insulation & horizontal cleat, flashings & trim, vertical wood cladding, and windows
- Lab Wing – East Elevation:
- Installing flashings and trim
- Start installing backer rod and caulk
- Lab Wing – South Elevation:
- Start installing vertical Z girt and windows
- INTERIOR BUILDOUT
- Mechanical & Back of House:
- Finish installing in-wall MEP at Electrical Rooms *
- Finish installing gyp top out *
- Start stuffing and spraying for STC’s
- Lab Wing Level 2 – Rough-in:
- Continue installing MEP in Labs
- Continue framing walls (starting at E/3 clockwise)
- SITE IMPROVEMENTS
- Mechanical Enclosure M0101:
- Stripping retaining walls, damp proofing walls, back filling walls, and forming sidewalks & steps
- Start placing sidewalk and steps at EOW
- ODF&W Parking and Sidewalks:
- Finish excavating for Public Rain Garden*
- Finish balance of storm work *
- Installing pole base and electrical for exterior light poles
- Start forming sidewalks and mono curbs