Primary construction activities for the week of 06/17 thru 06/21 will consist of the following:

 * = Start or Finish was delayed

  • ROOFING
  • Evacuation Ramp:
    • Finish Hot rubber roofing *
    • Form and install foam at 1st 3rd of the Ramp
  • High Roof Auditorium:
    • Start installing zinc roofing
  • Low Roof Auditorium:
    • Continue installing foam into Epic deck, insulation, and cover board
  • Lab Wing Main Roof:
    • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
  • Penthouses:
    • Finish installing framing *
    • Start installing sheathing *
  • Lab High Roof West:
    • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
  • Lab Wing – South Elevation:
    • Finish installing air & water barrier
    • Continue installing flashing at pop outs, window steel at pop outs
    • Start installing temp window protection (if needed)

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
  • Finish installing window steel at head & sill, flashings, air & water barrier, and temp window protection (of needed)*
    • Lab Wing – North Elevation:
  • Finish installing window steel at window head & sill, flashings, and air & water barrier, and temp window protection (if needed) *
    • Lab Wing – East Elevation:
  • Finish installing window steel at window head & sill, flashings, and air & water barrier
  • Start installing temp window protection (if needed) *
    • Lab Wing – South Elevation:
  • Continue installing steel studs

 

 

  • Auditorium – North Elevation:
    • Continue installing steel studs
      • Auditorium – South Elevation:
    • Finish installing steel stud floor clips *
    • Continue installing steel studs *
  • Auditorium – West Elevation:
    • Finish installing steel stud floor clips *
  • Innovation Lab:
    • Installing window steel

 

  • WINDOWS & SIDING
  • Lab Wing – West Elevation:
    • Continue installing vertical wood cladding
  • Lab Wing – North Elevation:
    • Continue installing insulation & horizontal cleat, flashings & trim, vertical wood cladding, and windows
  • Lab Wing – East Elevation:
    • Installing flashings and trim
    • Start installing backer rod and caulk
  • Lab Wing – South Elevation:
    • Start installing vertical Z girt and windows

 

  • INTERIOR BUILDOUT
  • Mechanical & Back of House:
    • Finish installing in-wall MEP at Electrical Rooms *
    • Finish installing gyp top out *
    • Start stuffing and spraying for STC’s
  • Lab Wing Level 2 – Rough-in:
    • Continue installing MEP in Labs
    • Continue framing walls (starting at E/3 clockwise)

 

  • SITE IMPROVEMENTS
  • Mechanical Enclosure M0101:
    • Stripping retaining walls, damp proofing walls, back filling walls, and forming sidewalks & steps
    • Start placing sidewalk and steps at EOW
  • ODF&W Parking and Sidewalks:
    • Finish excavating for Public Rain Garden*
    • Finish balance of storm work *
    • Installing pole base and electrical for exterior light poles
    • Start forming sidewalks and mono curbs