Primary construction activities for the week of 06/10 thru 06/14 will consist of:

  • ROOFING
    • High Roof Auditorium:
      • Finish installing roof
    • Evacuation Ramp:
      • Start Hot rubber roofing *
    • Low Roof Auditorium:
      • Start installing foam into Epic deck
    • Lab Wing Main Roof:
      • Continue installing hot fluid-applied rubber asphalt (tying to exterior walls)
    • Penthouses:
      • Finish installing framing *
      • Start installing sheathing *
    • Lab High Roof West:
      • Continue installing roof

 

  • FRAMING SHEATING (2nd & 3rd Floor)
    • Lab Wing – North Elevation:
      • Finish installing temp window protection (if needed)
    • Lab Wing – East Elevation:
      • Finish installing temp window protection (if needed)
    • Lab Wing – South Elevation:
      • Start installing air & water barrier, window steel at pop outs, and flashing at pop outs

 

  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
      • Finish installing exterior gyp board, window steel at head & sill, flashings, and air & water barrier *
    • Lab Wing – North Elevation:
      • Finish installing window steel at window head & sill, flashings, and air & water barrier, and temp window protection *
    • Lab Wing – East Elevation:
      • Finish installing exterior gyp, air & water barrier, flashings, and window steel at head & sill *
    • Lab Wing – South Elevation:
      • Start installing steel studs *
    • Auditorium – North Elevation:
      • Continue installing steel studs
    • Auditorium – South Elevation:
      • Finish installing steel stud floor clips *
      • Continue installing steel studs *
    • Auditorium – West Elevation:
      • Finish installing steel stud floor clips *

 

  • WINDOWS & SIDING
    • Lab Wing – West Elevation:
      • Continue installing siding horizontal cleat
      • Start installing vertical siding wood cladding *
    • Lab Wing – North Elevation:
      • Continue installing windows
      • Start installing flashings and trim
    • Lab Wing – East Elevation:
      • Installing windows
      • Start installing vertical z girt

 

  • INTERIOR BUILDOUT
    • Mechanical & Back of House:
      • Finish installing in-wall MEP at Electrical Rooms
      • Finish installing gyp top out
    • Lab Wing Level 2 – Rough-in:
      • Continue installing MEP in Labs
      • Continue framing walls (starting at E/3 clockwise)

 

  • SITE IMPROVEMENTS
    • Mechanical Enclosure M0101:
      • Installing rebar, pouring, and stripping Generator Pad and footings *
    • ODF&W Parking and Sidewalks:
      • Finish balance of storm work *
      • Installing Storm FC Manhole No.1 and storm chambers
      • Excavating for Public Rain Garden

 

  • SITEWORK & UTILITIES
    • Finish installing potable water and fire water laterals

 

 * = Start or Finish was delayed

Print Friendly, PDF & Email

Leave a reply