Primary construction activities for the week of 06/03 thru 06/07 will consist of the following:
ZONING LEGEND
Z1 = East Commons Wing | Z2 = West Commons Wing | Z3 = West Lab Wing | Z4 = Middle of Lab Wing | Z5 = East Lab Wing
- ROOFING
- High Roof Auditorium:
- Continue installing roof
- Evacuation Ramp:
- Finish installing handrails
- Start Hot rubber roofing
- Penthouses:
- Finish installing framing
- Installing sheathing
- Lab High Roof West:
- Continue installing roof
- High Roof Auditorium:
- FRAMING SHEATING (2nd & 3rd Floor)
- Lab Wing – North Elevation:
- Finish installing flashings at pop outs
- Continue installing temp window protection (if needed)
- Lab Wing – East Elevation:
- Finish installing flashings at pop outs and air & water barrier
- Lab Wing – South Elevation:
- Finish installing steel studs
- Installing exterior gyp
- Lab Wing – North Elevation:
- FRAMING SHEATING (1st Floor)
- Lab Wing – West Elevation:
- Finish installing window steel at window head & sill, flashings, and air & water barrier
- Start installing temp windows (if needed)
- Lab Wing – North Elevation:
- Finish installing exterior gyp
- Start installing window steel at window head & sill, flashings, and air & water barrier
- Installing temp window protection (if needed)
- Lab Wing -East Elevation:
- Finish installing steel studs (was postponed)
- Installing exterior gyp
- Start installing window steel at window head & sill, flashings, and air & water barrier at EOW
- Installing temp window protection (if needed)
- Lab Wing – South Elevation:
- Start installing steel studs
- Auditorium – South Elevation:
- Continue installing steel studs
- Start installing exterior gyp
- Auditorium – West Elevation:
- Start installing steel studs
- Auditorium – North Elevation:
- Start installing steel studs
- Lab Wing – West Elevation:
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- Continue installing siding horizontal cleat
- Start installing vertical siding wood cladding
- Lab Wing – North Elevation:
- Continue installing vertical Z girts and windows
- Lab Wing – East Elevation:
- Start installing vertical Z girts and windows
- Lab Wing – West Elevation:
- INTERIOR BUILDOUT
- Mechanical & Back of House:
- Finish framing walls
- Installing in-wall MEP at Electrical Rooms
- Start installing gyp top out
- Lab Wing Level 2 – Rough-in:
- Continue installing MEP in Labs
- Start framing walls (starting at E/3 clockwise)
- Stair 1:
- Pouring stairs
- Mechanical & Back of House:
- SITE IMPROVEMENTS
- Mechanical Enclosure M0101:
- Installing rebar, pouring, and stripping Generator Pad and footings
- Forming and installing rebar at one retaining wall
- ODF&W Parking and Sidewalks:
- Installing balance of storm work
- Start installing pole base and electrical
- Ramp:
- Installing bentonite and fluid-applied waterproofing
- Mechanical Enclosure M0101:
- SITEWORK & UTILITIES
- Install potable water and fire water laterals