Primary construction activities for the week of 05/27 thru 05/31 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • ROOFING
    • High Roof Auditorium:
      • Continue installing roof
    • Evacuation Ramp:
      • Finish installing handrails
      • Finish installing expansion joint
      • Hot rubber roofing postponed to following week
    • Penthouses:
      • Continue installing framing
    • Lab High Roof West:
      • Continue installing roof
  • FRAMING SHEATING (2nd & 3rd Floor)
    • Lab Wing – North Elevation:
      • Finish installing air and water barrier
      • Continue installing flashings at pop outs
      • Start installing temp window protection
    • Lab Wing – East Elevation:
      • Finish installing window steel at pop outs
      • Continue installing flashings at pop outs and air & water barrier
    • Lab Wing – South Elevation:
      • Continue installing steel studs
  • FRAMING SHEATING (1st Floor)
    • Lab Wing – West Elevation:
      • Finish installing exterior gyp
      • Continue installing window steel at window head & sill, flashings, and air & water barrier
    • Lab Wing – North Elevation:
      • Finish installing steel studs
      • Start installing exterior gyp
    • Lab Wing – East Elevation:
      • Start installing steel studs
    • Lab Wing – South Elevation:
      • Finish installing top / bottom track and studs
    • Auditorium – South Elevation:
      • Finish installing steel stud floor clips
      • Start installing steel studs
    • Auditorium – West Elevation:
      • Start installing steel stud floor clips
  • WINDOWS & SIDING
    • Lab Wing – West Elevation:
      • Finish installing flashings, and trim
    • Lab Wing – North Elevation:
      • Start installing vertical Z girt and windows
  • INTERIOR BUILDOUT
    • Mechanical & Back of House:
      • Finish installing hollow metal doors
      • Continue framing walls
    • Lab Wing Level 2 – Rough-in:
      • Continue installing MEP in Labs
      • Start installing hollow metal doors
    • Mechanical & Back of House:
      • Finish installing hollow metal doors
    • Stair 1:
      • Continue finishing interior
  • SITE IMPROVEMENTS
    • Mechanical Enclosure M0101:
      • Layout and excavate for Generator Pad and footings and forming generator pad and footings
    • ODF&W Parking and Sidewalks:
      • Finish installing erosion control and site fencing
      • Excavating Rain Garden #2
      • Excavating public rain garden
      • Installing storm at Manhole #1 and storm chambers
    • Ramp:
      • Forming, installing rebar, pouring, and stripping lower corbel