Primary construction activities for the week of 05/27 thru 05/31 will consist of:
ZONING LEGEND
Z1 = East Commons Wing | Z2 = West Commons Wing | Z3 = West Lab Wing | Z4 = Middle of Lab Wing | Z5 = East Lab Wing
- ROOFING
- High Roof Auditorium:
- Continue installing roof
- Evacuation Ramp:
- Finish installing handrails
- Finish installing expansion joint
- Hot rubber roofing postponed to following week
- Penthouses:
- Continue installing framing
- Lab High Roof West:
- Continue installing roof
- High Roof Auditorium:
- FRAMING SHEATING (2nd & 3rd Floor)
- Lab Wing – North Elevation:
- Finish installing air and water barrier
- Continue installing flashings at pop outs
- Start installing temp window protection
- Lab Wing – East Elevation:
- Finish installing window steel at pop outs
- Continue installing flashings at pop outs and air & water barrier
- Lab Wing – South Elevation:
- Continue installing steel studs
- Lab Wing – North Elevation:
- FRAMING SHEATING (1st Floor)
- Lab Wing – West Elevation:
- Finish installing exterior gyp
- Continue installing window steel at window head & sill, flashings, and air & water barrier
- Lab Wing – North Elevation:
- Finish installing steel studs
- Start installing exterior gyp
- Lab Wing – East Elevation:
- Start installing steel studs
- Lab Wing – South Elevation:
- Finish installing top / bottom track and studs
- Auditorium – South Elevation:
- Finish installing steel stud floor clips
- Start installing steel studs
- Auditorium – West Elevation:
- Start installing steel stud floor clips
- Lab Wing – West Elevation:
- WINDOWS & SIDING
- Lab Wing – West Elevation:
- Finish installing flashings, and trim
- Lab Wing – North Elevation:
- Start installing vertical Z girt and windows
- Lab Wing – West Elevation:
- INTERIOR BUILDOUT
- Mechanical & Back of House:
- Finish installing hollow metal doors
- Continue framing walls
- Lab Wing Level 2 – Rough-in:
- Continue installing MEP in Labs
- Start installing hollow metal doors
- Mechanical & Back of House:
- Finish installing hollow metal doors
- Stair 1:
- Continue finishing interior
- Mechanical & Back of House:
- SITE IMPROVEMENTS
- Mechanical Enclosure M0101:
- Layout and excavate for Generator Pad and footings and forming generator pad and footings
- ODF&W Parking and Sidewalks:
- Finish installing erosion control and site fencing
- Excavating Rain Garden #2
- Excavating public rain garden
- Installing storm at Manhole #1 and storm chambers
- Ramp:
- Forming, installing rebar, pouring, and stripping lower corbel
- Mechanical Enclosure M0101: