Primary construction activities for the week of 05/06 thru 05/10 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • Northeast Wall (Pour 6):
      • Finish closing wall formwork, pouring, and stripping.
  • Structural Steel
    • Zone 1:
      • Finish installing metal decking and closure strips by EOW.
  • Slab on Grade
    • Zone 3 (South ½ of Z3 & Z4 and 65% of Z5):
      • Installing top embeds and pouring.
    • Zone 4 (North ½ of Z3 & Z4):
      • Finish installing blockouts and edge form.
      • Installing rebar, top embeds, and pouring.
    • Zone 5:
      • Installing top embeds and pouring.
  • Roofing
    • Evacuation Ramp
      • Installing 4 x 4 angle at Eyebrow.
      • Start installing handrails.
    • East Penthouse:
      • Pouring Slab-on Foam.
  • Framing Sheeting (2nd & 3rd Floor)
    • Lab Wing West & SW Elevation:
      • Finish installing window steel at pop-outs.
      • Start installing flashings at pop-outs.
    • Lab Wing North Elevation:
      • Finish installing exterior gyp.
      • Start installing air and water barrier, window steel at pop outs, and flashings at pop outs.
    • Lab Wing South Elevation
      • Finish installing steel stud floor clips.
  • Penthouses
    • Start installing framing
  • Framing Sheeting (1st Floor)
    • Auditorium Misc. Steel and Wind Girts
      • Finish setting Auditorium mezzanine steel.
    • Auditorium North Elevation
      • Finish installing steel stud floor clips.
    • Auditorium East Elevation
      • Finish installing steel stud floor clips.
    • Windows and Siding
      • West Elevation
        • Finish installing vertical Z Girt and windows.
        • Start installing backer rods and caulking.
  • Site Improvements
    • Mechanical Enclosure M0101
      • Excavating for electrical and chilled water.
    • Ramp
      • Installing Bentonite and fluid applied waterproofing, foundation drain, back fill and grade for foam.
      • Start installing foam at EOW.