Primary construction activities for the week of 04/29 thru 05/03 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • Northeast Wall (Pour 6):
      • Finish closing wall formwork, pouring, and stripping.
  • Structural Steel
    • Zone 1:
      • Finish installing metal decking and closure strips by EOW.
  • Slab on Grade
    • Zone 3 (South ½ of Z3 & Z4 and 65% of Z5):
      • Installing blockouts, edge form, electrical, and importing rock & grade.
      • Installing vapor barrier and rebar.
    • Zone 4 (North ½ of Z3 & Z4):
      • Installing electrical and final grading of native.
      • Importing rock & grade, installing blockouts, edge form, and vapor barrier.
    • Zone 5:
      • Importing rock & grade, installing blockouts, edge form, vapor barrier, and rebar.
  • Roofing
    • Evacuation Ramp
      • Cleaning embeds and roof area.
      • Installing framing on GL-8 above and North of ramp.
    • Lab Wing Main Roof:
      • West Penthouse:
        • Forming, installing rebar, and pouring curbs
        • Pouring Slab-on-Foam.
      • East Penthouse:
        • Finish welding, bolting, and decking.
        • Installing formwork, rebar, and pouring curbs.
  • Framing Sheeting
    • Lab Wing West & SW Elevation:
      • Start installing exterior gyp board, flashings at pop-outs, window steel at pop-outs, and air & water barrier.
    • Lab Wing North Elevation:
      • Continue installing steel studs.
    • Lab Wing East Elevation:
      • Finish installing steel stud floor clips.
    • Lab Wing South Elevation
      • Start installing steel stud floor clips.

 

  • Sitework & Utilities
    • Installing Potable and Fire water laterals.
Print Friendly, PDF & Email

Leave a reply