Primary construction activities for the week of 04/29 thru 05/03 will consist of:
ZONING LEGEND
Z1 = East Commons Wing | Z2 = West Commons Wing | Z3 = West Lab Wing | Z4 = Middle of Lab Wing | Z5 = East Lab Wing
- Ramp
- Northeast Wall (Pour 6):
- Finish closing wall formwork, pouring, and stripping.
- Northeast Wall (Pour 6):
- Structural Steel
- Zone 1:
- Finish installing metal decking and closure strips by EOW.
- Zone 1:
- Slab on Grade
- Zone 3 (South ½ of Z3 & Z4 and 65% of Z5):
- Installing blockouts, edge form, electrical, and importing rock & grade.
- Installing vapor barrier and rebar.
- Zone 4 (North ½ of Z3 & Z4):
- Installing electrical and final grading of native.
- Importing rock & grade, installing blockouts, edge form, and vapor barrier.
- Zone 5:
- Importing rock & grade, installing blockouts, edge form, vapor barrier, and rebar.
- Zone 3 (South ½ of Z3 & Z4 and 65% of Z5):
- Roofing
- Evacuation Ramp
- Cleaning embeds and roof area.
- Installing framing on GL-8 above and North of ramp.
- Lab Wing Main Roof:
- West Penthouse:
- Forming, installing rebar, and pouring curbs
- Pouring Slab-on-Foam.
- East Penthouse:
- Finish welding, bolting, and decking.
- Installing formwork, rebar, and pouring curbs.
- West Penthouse:
- Evacuation Ramp
- Framing Sheeting
- Lab Wing West & SW Elevation:
- Start installing exterior gyp board, flashings at pop-outs, window steel at pop-outs, and air & water barrier.
- Lab Wing North Elevation:
- Continue installing steel studs.
- Lab Wing East Elevation:
- Finish installing steel stud floor clips.
- Lab Wing South Elevation
- Start installing steel stud floor clips.
- Lab Wing West & SW Elevation:
- Sitework & Utilities
- Installing Potable and Fire water laterals.