Primary construction activities for the week of 04/22/19 thru 04/26/19 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • Northeast Wall (Pour 6):
      • Setting wall formwork and installing wall rebar.
  • Structural Steel
    • Zone 1:
      • Finish installing metal decking and closure strips by EOW
  • Slab on Metal Deck
    • Zone 5 Level 2:
      • Curing deck for reshore removal
  • Slab on Grade
    • Zone 2:
      • Pouring slab
    • Zone 3:
      • Installing potable water, sanitary sewer & storm, and electrical
    • Zone 4:
      • Installing sanitary sewer & storm and potable water
    • Zone 5:
      • Installing potable water, sanitary sewer & storm, and electrical
  • Roofing
    • High Roof Auditorium:
      • Start installing roofing
    • Lab Wing Main Roof:
      • Forming and installing rebar at West curbs
      • West Penthouse:
        • Forming, installing rebar, and pouring curbs
      • East Penthouse:
        • Welding, bolting, and decking
        • Forming curbs
      • Lab High Roof East:
        • Continue installing roofing
    • Lab High Roof West:
      • Continue installing roofing
    •  Canopies:
      • Start installing roofing
  • Framing Sheeting
    • Lab Wing West & SW Elevation:
      • Continue installing steel studs
    • Lab Wing North Elevation:
      • Continue installing steel stud floor clips
    • Lab Wing East Elevation:
      • Continue installing steel stud floor clips
    • Miscellaneous Steel & Wind Girts
      • Auditorium:
        • Setting mezzanine steel