Primary construction activities for the week of 04/22/19 thru 04/26/19 will consist of:
ZONING LEGEND
Z1 = East Commons Wing | Z2 = West Commons Wing | Z3 = West Lab Wing | Z4 = Middle of Lab Wing | Z5 = East Lab Wing
- Ramp
- Northeast Wall (Pour 6):
- Setting wall formwork and installing wall rebar.
- Northeast Wall (Pour 6):
- Structural Steel
- Zone 1:
- Finish installing metal decking and closure strips by EOW
- Zone 1:
- Slab on Metal Deck
- Zone 5 Level 2:
- Curing deck for reshore removal
- Zone 5 Level 2:
- Slab on Grade
- Zone 2:
- Pouring slab
- Zone 3:
- Installing potable water, sanitary sewer & storm, and electrical
- Zone 4:
- Installing sanitary sewer & storm and potable water
- Zone 5:
- Installing potable water, sanitary sewer & storm, and electrical
- Zone 2:
- Roofing
- High Roof Auditorium:
- Start installing roofing
- Lab Wing Main Roof:
- Forming and installing rebar at West curbs
- West Penthouse:
- Forming, installing rebar, and pouring curbs
- East Penthouse:
- Welding, bolting, and decking
- Forming curbs
- Lab High Roof East:
- Continue installing roofing
- Lab High Roof West:
- Continue installing roofing
- Canopies:
- Start installing roofing
- High Roof Auditorium:
- Framing Sheeting
- Lab Wing West & SW Elevation:
- Continue installing steel studs
- Lab Wing North Elevation:
- Continue installing steel stud floor clips
- Lab Wing East Elevation:
- Continue installing steel stud floor clips
- Miscellaneous Steel & Wind Girts
- Auditorium:
- Setting mezzanine steel
- Auditorium:
- Lab Wing West & SW Elevation: