Primary construction activities for the week of 04/15 thru 04/19 will consist of:
ZONING LEGEND
Z1 = East Commons Wing | Z2 = West Commons Wing | Z3 = West Lab Wing | Z4 = Middle of Lab Wing | Z5 = East Lab Wing
- Ramp
- East Storage Room & Northeast Wall (Pour 4):
- Closing formwork, pouring, and stripping wall
- South Wall East Portion (Pour 5):
- Setting wall formwork
- East Storage Room & Northeast Wall (Pour 4):
- Structural Steel
- Zone 1:
- Finish installing metal decking and closure strips early next week
- Zone 1:
- Slab on Metal Deck
- Zone 5 Level 3:
- Curing deck for reshore removal
- Zone 4 Level 2:
- Finish installing rebar; installing top embeds and pouring deck
- Zone 5 Level 2
- Installing rebar, top embeds, and pouring deck
- Zone 5 Level 3:
- Slab on Grade
- Zone 1:
- Installing top embeds and pouring slab
- Zone 2:
- Installing rebar, top embeds, and pouring slab
- Zone 1:
- Roofing
- Lab Wing Main Roof:
- Forming and installing rebar at West curbs
- West Penthouse:
- Welding, bolting, and decking
- East Penthouse:
- Welding, bolting, and decking
- Lab High Roof East:
- Continue installing roof
- Lab High Roof West:
- Continue installing roof
- Lab Wing Main Roof:
- Framing Sheeting
- Lab Wing West & SW Elevation:
- Installing steel studs
- Lab Wing North Elevation:
- Installing steel stud floor clips
- Lab Wing East Elevation:
- Installing steel stud floor clips
- Lab Wing West & SW Elevation: