Primary construction activities for the week of 04/08/19 thru 04/12/19 will consist of:
ZONING LEGEND
Z1 = East Commons Wing | Z2 = West Commons Wing | Z3 = West Lab Wing | Z4 = Middle of Lab Wing | Z5 = East Lab Wing
- Ramp
- East Storage Rm & Northeast Wall (Pour 4):
- Closing formwork, pouring, and stripping wall
- South Wall East Portion (Pour 5):
- Setting wall formwork
- Structural Steel
- Zone 1:
- Finish installing metal decking and closure strips
- Slab on Metal Deck
- Zone 4 Level 3:
- Pouring deck and curing deck for Reshore removal
- Zone 3 Level 2:
- Finish installing rebar, top embeds, pouring deck, and curing deck for Reshore removal
- Zone 5 Level 3:
- Finish installing rebar, top embeds and QA/QC deck
- Zone 4 Level 2:
- Installing rebar
- Slab on Grade
- Zone 1:
- Installing top embeds and pouring slab
- Zone 2:
- Installing vapor barrier, stripping at GL-N, and back filling at GL-N
- Installing rebar, top embeds, and QA/QC pour
- Roofing
- Lab Wing High Roof:
- Set West and East Penthouse steel
- Set Elevator spreader tubes
- Weld bolt and deck at West Penthouse
- Lab High Roof East
- Continue installing roof
- Framing Sheeting
- Lab Wing West & SW Elevation:
- Installing steel stud floor clips
- Lab Wing North Elevation
- Installing steel stud floor clips
- Lab Wing West & SW Elevation:
- Lab Wing High Roof:
- Zone 1:
- Zone 4 Level 3:
- Zone 1:
- East Storage Rm & Northeast Wall (Pour 4):