Primary construction activities for the week of 04/08/19 thru 04/12/19 will consist of:

ZONING LEGEND

Z1 = East Commons Wing  |  Z2 = West Commons Wing  |  Z3 = West Lab Wing  |  Z4 = Middle of Lab Wing   |  Z5 = East Lab Wing

  • Ramp
    • East Storage Rm & Northeast Wall (Pour 4):
      • Closing formwork, pouring, and stripping wall
    • South Wall East Portion (Pour 5):
      • Setting wall formwork
    • Structural Steel
      • Zone 1:
        • Finish installing metal decking and closure strips
      • Slab on Metal Deck
        • Zone 4 Level 3:
          • Pouring deck and curing deck for Reshore removal
        • Zone 3 Level 2:
          • Finish installing rebar, top embeds, pouring deck, and curing deck for Reshore removal
        • Zone 5 Level 3:
          • Finish installing rebar, top embeds and QA/QC deck
        • Zone 4 Level 2:
          • Installing rebar
        • Slab on Grade
          • Zone 1:
            • Installing top embeds and pouring slab
          • Zone 2:
            • Installing vapor barrier, stripping at GL-N, and back filling at GL-N
            • Installing rebar, top embeds, and QA/QC pour
          • Roofing
            • Lab Wing High Roof:
              • Set West and East Penthouse steel
              • Set Elevator spreader tubes
              • Weld bolt and deck at West Penthouse
            • Lab High Roof East
              • Continue installing roof
            • Framing Sheeting
              • Lab Wing West & SW Elevation:
                • Installing steel stud floor clips
              • Lab Wing North Elevation
                • Installing steel stud floor clips
Print Friendly, PDF & Email

Leave a reply