Primary construction activities for the week of 03/25/2019 thru 03/29/2019:
- Ramp
- North Radius Wall (Pour 2):
- Strip formwork.
- South Wall West (Pour 3):
- Finish setting wall and installing rebar.
- North Radius Wall (Pour 2):
- Structural Steel
- East Lab Wing (Z5):
- Finish bolting, plumbing, and welding.
- Start installing metal decking and closure strips.
- East Lab Wing (Z5):
- Slab on Metal Deck
- West Commons Wing Roof (Z2):
- Pouring at beginning of week
- West Lab Wing Roof (Z3 & ½ Z4):
- Installing rebar, top embeds, and pouring deck
- West Lab Wing L3 (Z3):
- Installing rebar, and top embeds
- West Lab Wing L2 (Z3)
- Installing blockouts, down embeds and shoring
- West Commons Wing Roof (Z2):
- Slab on Grade
- East Commons Wing:
- Installing sanitary sewer and storm, electrical, potable water, blockouts and edge form, and grading.
- West Commons Wing
- Installing electrical, potable water, sanitary sewer and storm, installing block outs and edge form, and grading.
- East Commons Wing:
- Roofing
- Lab Wing High Roof:
- Start forming curbs and crickets at end of week.
- Lab Wing High Roof: