Primary construction activities for the week of 03/11/2019 thru 03/15/2019:
- Ramp:
- Pour 2 (North Radius Wall):
- Finish stripping wall.
- Pour 3 (South Wall West):
- Setting wall and installing rebar.
- Pour 2 (North Radius Wall):
- Structural Steel:
- Stair 2:
- Finish install of handrails.
- East Commons (Z1):
- Finish install of metal decking and closure strips.
- West Lab Wing (Z3):
- Installing headed studs.
- Center Lab Wing (Z4):
- Finish bolting, plumbing, and welding.
- Install metal decking and closure strips.
- East Lab Wing (Z5):
- Bolting, plumbing, and welding
- Stair 2:
- Slab on Metal Deck
- Z2 Roof:
- Installing blockouts and down embeds
- Installing rebar
- Installing top embeds
- Z2 L2:
- Installing blockouts and down embeds
- Installing rebar
- Z2 Roof:
- Sitework & Utilities
- Install potable and fire water laterals
- Mockup:
- Finish installing siding.