Primary construction activities for the week of 2/18/2019 – 2/22/2019 will consist of:
Ramp- setting wall formwork, installing wall rebar, and closing formwork.
Structural Steel-
Stair 2- Installing clips, hangers, stairs, and handrails.
East Commons (Z1)- Installing metal decking and closure strips.
West Commons (Z2)- Bolting, plumbing, and welding. Installing metal decking and closure strips.
West Lab Wing (Z3)- Erecting steel, bolting, plumbing, and welding.
Center Lab Wing (Z4)- Erecting steel.
Mockup- Installing windows, green girts, and flashing behind green girts.