Primary Construction Activites for 02/04/2019-02/08/2019:
Core 1: Forming and pouring architectural fur wall.
Core 3: stripping level 4 core exterior.
Ramp: Stripping South and North footings. Fabricating walls and setting wall formwork.
Structural Steel: Stair 1- Installing stair and handrails.
Stair 2- Installing stair and handrails.
East Commons (Z1): Erecting steel, bolting, welding, and plumbing.
West Commons (Z2): Installing shear tab clips and misc. metals.
West Lab Wing (Z3): Installing Shear tab clips and misc. metals.
Mockup: Framing, installing steel window surround, backing, and weather barrier.