Primary construction activities for the week of 1/28/2019 – 2/1/2019 will consist of:
Core 1- Forming and pouring architectural fur wall.
Core 2- Level 4 will have rebar placed, formwork closed, and be poured.
Core 3- Level 4 will have rebar placed, formwork closed, and be poured.
Ramp- Forming and placing rebar, and pouring footings at the South wall.
Slab for Level 1 Air Handler Unit- pouring then striping the forms.
Mockups- Framing and sheeting.
Structural Steel- Stair 1 installing handrail.
– East Commons (Z1) installing shear tab clips. erecting steel Friday 2/10.
– West Commons (Z2) installing shear tab clips and misc. Metals.