Primary construction activities for the week of 1/14/2019-1/18/2019 consist of:
Core 1- Level 4 Will have rebar and formwork set. Core 1 will also have a structural patch fix that will require jackhammering with a water wash.
Core 2- Level 3 will have rebar set, closing in formwork, and begin pouring level 3.
Core 3- Level 2 will be poured and stripped, then the forms will be moved up to level 3 and begin setting rebar.
Slab for Level 1 Air Handler Unit- will have drain rock and vapor barrier placed, then rebar for the slab will be set.
Mockups for installing steel window surrounds, backing, and weather barrier will be constructed.