Primary construction activities for the week of December 3rd through December 7th:

Forming and pouring of:

  • Core wall Zone 1 Level 2
  • Shear walls Zone 2 and 4 Level 3
  • Shear wall Zone 3 level 2
  • Shear wall Zone 1 and 5 Level 2

Backfilling continuous footings and East mat.