Primary construction activities for the week of 11/26 thru 11/30 will consist of the following:

Continued forming and pouring of all shear walls and core walls.

    • Stripping core Zone 1 level 1.
    • Pouring shear walls Zones 2, 3, and 4 level 2.
    • Continuing form work for shear walls in Zones 1 and 5.
    • Back filling East Mat.
Print Friendly, PDF & Email

Leave a reply