Primary construction activities for the week of 11/26 thru 11/30 will consist of the following:
Continued forming and pouring of all shear walls and core walls.
-
- Stripping core Zone 1 level 1.
- Pouring shear walls Zones 2, 3, and 4 level 2.
- Continuing form work for shear walls in Zones 1 and 5.
- Back filling East Mat.