Primary construction activities for the week of 10/22 thru 10/26 will consist of the following:
- Installing asphalt walk at ODFW / West Wing
- Installing Rebar, pouring, and stripping Continuous Footings
- Pouring concrete and stripping at East Mat Footing (attached Images)
- One-side formwork for Shear Walls 1, 2, and 3
- Installing rebar at Shear Walls 4 and 5
- Forming and installing rebar for Level 1 of Core 1
- Forming and installing rebar for Starter Wall at Core 2 & 3
Attached Schedule