The primary construction activities this week include:

Placement of rebar and pouring of concrete for the shear wall footings.

Forming, rebar placement, and pouring of concrete for the west mat footing.

Rocking and forming for the east mat footing.

Waterline shutdown for tie in at Guin Library Tuesday October 9th from 7:00am to 9:00am

Waterline shutdown for tie in at Housing and Dining Friday October 12th from 11:00am to 2:00pm.

Print Friendly, PDF & Email

Leave a reply