Primary construction activities for the week of 9/17 thru 9/21 will consist of the following:

JAFEC and the Deep Soil Mixing equipment, will be demobilized 09/19.

Fiber work to ODF&W scheduled for 09/20 – 09/26, Access on foot path closed between OF&W and Ship Ops.

New water service work scheduled for 09/17, Ferry Slip Road will be closed for deliveries.

Coring in Lab Wing finished 09/19.

Attached is an up to date schedule for the project.