Primary construction activities for this week will include:
Continued Deep Soil Mixing for the Lab Wing. Expect constant vibrations.
Grinding of Deep Soil Mixing columns to final elevation.
Finance and Administration / Design and Construction
Primary construction activities for this week will include:
Continued Deep Soil Mixing for the Lab Wing. Expect constant vibrations.
Grinding of Deep Soil Mixing columns to final elevation.