Primary construction activities for this will include continued mobilization of Deep Soil Mixing equipment throughout the week and a waterline shutdown mid-week.

The waterline shutdown will take place Wednesday June 27th from 5:00 pm to 11:00 pm. This will effect water to the Visitors Center, East Wing, West Wing, Education Wing, Guin Library, NAL RSF, and Housing.

Below is an up to date schedule for the site.

MSIB CC 2018.06.11 schedule

Print Friendly, PDF & Email

Leave a reply