Primary activities this week include continued installation of the new water line. Starting Wednesday June 20th expect to see the arrival of the deep soil mixing equipment. Expect to see several large trucks delivering parts and machinery and parts to set up the drill rig, crane, and mixing plant.
Below is an up to date schedule for the site