{"id":423,"date":"2019-07-24T17:46:47","date_gmt":"2019-07-24T17:46:47","guid":{"rendered":"http:\/\/blogs.oregonstate.edu\/magruderproject\/?p=423"},"modified":"2019-07-24T17:46:52","modified_gmt":"2019-07-24T17:46:52","slug":"weekly-update-7-22-7-26","status":"publish","type":"post","link":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/2019\/07\/24\/weekly-update-7-22-7-26\/","title":{"rendered":"Weekly Update: 7\/22-7\/26"},"content":{"rendered":"\n<p>At the Clinic, the metal panels at the connector will be installed. As well as, the windows and those glass glazing throughout the clinic and the cabinetry will also be getting installed this week.  The second floor of the clinic will also see sheetrock and framing and the mechanical, electrical and plumbing rough-ins. <\/p>\n\n\n\n<p>The lobby will have framing going up to tie-in the existing lobby to the new addition.  The lobby will also be getting its roof and having the concrete slab poured-back. <\/p>\n\n\n\n<p>The lecture hall will have the exterior site prepped and inside the concrete will be getting a nice polish. <\/p>\n\n\n\n<p>the mechanical, electrical, and plumbing rough-ins continue at LINAC and the finishing on the walls will be going up. <\/p>\n\n\n\n<p>Outside in the parking lot, concrete pours will continue for curbs and sidewalks. <\/p>\n","protected":false},"excerpt":{"rendered":"<p>At the Clinic, the metal panels at the connector will be installed. As well as, the windows and those glass glazing throughout the clinic and the cabinetry will also be getting installed this week. The second floor of the clinic will also see sheetrock and framing and the mechanical, electrical and plumbing rough-ins. The lobby &hellip; <\/p>\n<p class=\"link-more\"><a href=\"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/2019\/07\/24\/weekly-update-7-22-7-26\/\" class=\"more-link\">Continue reading<span class=\"screen-reader-text\"> &#8220;Weekly Update: 7\/22-7\/26&#8221;<\/span><\/a><\/p>\n","protected":false},"author":9198,"featured_media":0,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"jetpack_post_was_ever_published":false,"_jetpack_newsletter_access":"","_jetpack_dont_email_post_to_subs":false,"_jetpack_newsletter_tier_id":0,"_jetpack_memberships_contains_paywalled_content":false,"_jetpack_memberships_contains_paid_content":false,"footnotes":"","jetpack_publicize_message":"","jetpack_publicize_feature_enabled":true,"jetpack_social_post_already_shared":true,"jetpack_social_options":{"image_generator_settings":{"template":"highway","default_image_id":0,"font":"","enabled":false},"version":2}},"categories":[1],"tags":[],"class_list":["post-423","post","type-post","status-publish","format-standard","hentry","category-uncategorized"],"jetpack_publicize_connections":[],"jetpack_featured_media_url":"","jetpack_sharing_enabled":true,"jetpack_shortlink":"https:\/\/wp.me\/pa9x0N-6P","jetpack-related-posts":[{"id":416,"url":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/2019\/07\/17\/weekly-update-7-15-7-18\/","url_meta":{"origin":423,"position":0},"title":"Weekly Update: 7\/15-7\/18","author":"raygr","date":"July 17, 2019","format":false,"excerpt":"It's a very busy week for the Magruder Hall Expansion, at the clinic the light fixture and electrical trim are being installed and the metal panels will be installed at the connector. The clinic storefront windows will continue to be installed, as well as the casework. The second floor of\u2026","rel":"","context":"Similar post","block_context":{"text":"Similar post","link":""},"img":{"alt_text":"","src":"","width":0,"height":0},"classes":[]},{"id":391,"url":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/2019\/07\/08\/hitting-it-hard-after-the-4th-weekly-update-7-8-7-12\/","url_meta":{"origin":423,"position":1},"title":"Hitting it Hard After the 4th; Weekly Update 7\/8-7\/12","author":"raygr","date":"July 8, 2019","format":false,"excerpt":"After celebrating America's Independence last Thursday, July 4th, crews are ready to get back to work for another busy week! At the clinic, the first floor will see the electrical fixtures go up and the installation of trim will begin. Also, the clinic connector metal panel will be installed at\u2026","rel":"","context":"Similar post","block_context":{"text":"Similar post","link":""},"img":{"alt_text":"","src":"https:\/\/i0.wp.com\/blogs.oregonstate.edu\/magruderproject\/files\/2019\/07\/IMG_5182.jpg?resize=350%2C200","width":350,"height":200,"srcset":"https:\/\/i0.wp.com\/blogs.oregonstate.edu\/magruderproject\/files\/2019\/07\/IMG_5182.jpg?resize=350%2C200 1x, https:\/\/i0.wp.com\/blogs.oregonstate.edu\/magruderproject\/files\/2019\/07\/IMG_5182.jpg?resize=525%2C300 1.5x, https:\/\/i0.wp.com\/blogs.oregonstate.edu\/magruderproject\/files\/2019\/07\/IMG_5182.jpg?resize=700%2C400 2x, https:\/\/i0.wp.com\/blogs.oregonstate.edu\/magruderproject\/files\/2019\/07\/IMG_5182.jpg?resize=1050%2C600 3x, https:\/\/i0.wp.com\/blogs.oregonstate.edu\/magruderproject\/files\/2019\/07\/IMG_5182.jpg?resize=1400%2C800 4x"},"classes":[]},{"id":369,"url":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/2019\/06\/18\/magruder-update-6-18\/","url_meta":{"origin":423,"position":2},"title":"Magruder Update 6\/18","author":"raygr","date":"June 18, 2019","format":false,"excerpt":"Currently at the addition of the clinic, the second floor is having the ducting installed for the heating and cooling system and the clinic overall will start to see paint go up on the walls. The latter half of the week, crews will start to install fixtures and the ceiling\u2026","rel":"","context":"Similar post","block_context":{"text":"Similar post","link":""},"img":{"alt_text":"","src":"https:\/\/i0.wp.com\/osu-wams-blogs-uploads.s3.amazonaws.com\/blogs.dir\/3227\/files\/2019\/06\/IMG_0022.jpg?resize=350%2C200","width":350,"height":200,"srcset":"https:\/\/i0.wp.com\/osu-wams-blogs-uploads.s3.amazonaws.com\/blogs.dir\/3227\/files\/2019\/06\/IMG_0022.jpg?resize=350%2C200 1x, https:\/\/i0.wp.com\/osu-wams-blogs-uploads.s3.amazonaws.com\/blogs.dir\/3227\/files\/2019\/06\/IMG_0022.jpg?resize=525%2C300 1.5x"},"classes":[]},{"id":169,"url":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/2018\/10\/22\/10-22-10-26-weekly-update-moving-upward-and-onward\/","url_meta":{"origin":423,"position":3},"title":"10\/22-10\/26 weekly update, moving upward and onward!","author":"raygr","date":"October 22, 2018","format":false,"excerpt":"This week, Fortis will start off working hard to remove the forms, from last weeks foundation concrete pour and doing a general clean up related to the foundation of the clinic. Fortis will continue to make way for additional clinic parking and finish off clearing the island in the hospital\u2026","rel":"","context":"Similar post","block_context":{"text":"Similar post","link":""},"img":{"alt_text":"","src":"https:\/\/i0.wp.com\/osu-wams-blogs-uploads.s3.amazonaws.com\/blogs.dir\/3227\/files\/2018\/10\/fe7c2065bba1feb7b642988135c1b3de.jpg?resize=350%2C200","width":350,"height":200,"srcset":"https:\/\/i0.wp.com\/osu-wams-blogs-uploads.s3.amazonaws.com\/blogs.dir\/3227\/files\/2018\/10\/fe7c2065bba1feb7b642988135c1b3de.jpg?resize=350%2C200 1x, https:\/\/i0.wp.com\/osu-wams-blogs-uploads.s3.amazonaws.com\/blogs.dir\/3227\/files\/2018\/10\/fe7c2065bba1feb7b642988135c1b3de.jpg?resize=525%2C300 1.5x, https:\/\/i0.wp.com\/osu-wams-blogs-uploads.s3.amazonaws.com\/blogs.dir\/3227\/files\/2018\/10\/fe7c2065bba1feb7b642988135c1b3de.jpg?resize=700%2C400 2x"},"classes":[]},{"id":365,"url":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/2019\/05\/20\/5-20-weekly-update\/","url_meta":{"origin":423,"position":4},"title":"5\/20 Weekly Update","author":"raygr","date":"May 20, 2019","format":false,"excerpt":"This week at the new clinic, the weest wall will have its brick cladding installed, which will be finished by the end of the week. Also happening at the clinic, crews will get started on the interior epoxy floors. This work will continue through this week and to the end\u2026","rel":"","context":"Similar post","block_context":{"text":"Similar post","link":""},"img":{"alt_text":"","src":"","width":0,"height":0},"classes":[]},{"id":307,"url":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/2019\/02\/18\/a-presidential-weekly-update-2-18-2-22\/","url_meta":{"origin":423,"position":5},"title":"A Presidential Weekly Update: 2\/18-2\/22","author":"raygr","date":"February 18, 2019","format":false,"excerpt":"As we kick this week off with Presidents Day, our crew continues to blast through construction, like the blasts that created our founding fathers on Mt. Rushmore. Once again, the majority of the work this week will be happening at the clinic. The exterior stub walls are still going up\u2026","rel":"","context":"Similar post","block_context":{"text":"Similar post","link":""},"img":{"alt_text":"","src":"","width":0,"height":0},"classes":[]}],"_links":{"self":[{"href":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/wp-json\/wp\/v2\/posts\/423","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/wp-json\/wp\/v2\/users\/9198"}],"replies":[{"embeddable":true,"href":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/wp-json\/wp\/v2\/comments?post=423"}],"version-history":[{"count":1,"href":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/wp-json\/wp\/v2\/posts\/423\/revisions"}],"predecessor-version":[{"id":424,"href":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/wp-json\/wp\/v2\/posts\/423\/revisions\/424"}],"wp:attachment":[{"href":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/wp-json\/wp\/v2\/media?parent=423"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/wp-json\/wp\/v2\/categories?post=423"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/dev.blogs.oregonstate.edu\/magruderproject\/wp-json\/wp\/v2\/tags?post=423"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}