Weekly Update: 8/6-8/9

The lecture hall will have the storm drain going in this week. Inside the lecture hall the flooring will be installed, as well as the vestibule installation.

The clinic’s activities will be carrying on from last week, the window frames will be installed, with the 2nd floor drywall and overall flooring in the building. Also, the metal lab casework will be getting installed.

At LINAC, they are still moving on the mechanical, electrical and plumbing rough-ins and working on miscellaneous site concrete.

Print Friendly, PDF & Email

Leave a Reply