Hitting it Hard After the 4th; Weekly Update 7/8-7/12

After celebrating America’s Independence last Thursday, July 4th, crews are ready to get back to work for another busy week!

At the clinic, the first floor will see the electrical fixtures go up and the installation of trim will begin. Also, the clinic connector metal panel will be installed at the same time as the storefront frame and windows are being installed, and the first floor casework will begin to go in at the end of the week. The second floor of the clinic will see less overall activity, but will still have lots going on as the mechanical, plumbing and electrical lines get roughed-in.

The lecture hall will be simple yet busy this week. All the fixtures in the lecture will be installed this week, as well as all of the glass glazing. Also, the casework will begin to go in this week and will continue through next week.

LINAC is having the mechanical and plumbing rough-in finished up this week in anticipation of sheetrock going up next week.

The lobby will be taking more shape this week as the under slab mechanical, plumbing and electrical rough in is finished and the concrete will be poured back. The lobby will also have the wall framing taking place this week.

The parking lot also continues as they pour concrete for light poles, curbs and walkways early this week followed by prepping the parking lot for the first lift of paving on Thursday the 11th.

Print Friendly, PDF & Email

Leave a Reply