The clinic will be shaping up this week as crews work on installing the metal panels and window frames. The second floor will have additional work going on, as the sheetrock also gets installed this week.

The lecture hall will continue to have the installation of the glass glazing, which is a continuation from last week. New this week, fixtures for the lecture hall will be installed beginning this week.

In what will be the new parking parking lot by the clinic and new entrance to the small animal hospital, underground utilities will be put down into place.

Wrapping up with the progress at LINAC, crews are still continuing with electrical, mechanical and plumbing rough in.

More photos can be found under the photos tab!