As we jump into the month of May, Construction continues on at the new Clinic and Lecture hall at the Magruder Hall Expansion Project. As everyone is able to enjoy this beautiful weather, the first floor of the clinic will see the sheet rock go up and the outer brick veneer continues to be installed. As the new clinic become incorporated into the existing Magruder Hall, the existing lobby will be going through work roughing in for new electrical.
The focus at the new Lecture hall will also center around the electrical rough in this week and the demo’d parking lot will be going through excavation to make room for more parking to service the new clinic.