Pushing through MLK jr. Day- Weekly Update 1/21-1/25

As the OSU community enjoyed a extended weekend in celebration of Martin Luther King Jr. Day, Monday the 21st, Fortis and their team were hard at work continuing with the Magruder Expansion.

The next several weeks are planned to be very busy over the three site locations and tying in with the existing Magruder Hall.

At the clinic, T. Gerding will be working on the exterior stub walls. While WPI will finish out the exterior framing of the east side of the clinic today and complete the south side framing from Wednesday through Friday.  Overlying the entire week, WPI will be installing exterior sheeting which is planned to carry over to next week. Hammerquist plans on finishing up the rain drain piping on the first floor by mid-week and start the rain drain piping on the second floor. Finally at the clinic, Pacific Excavation will begin digging for the vestibule, which is a small room next to the outer door and connecting it with the interior of the building.

Over at the new lecture hall, T. Gerding will be installing the exterior stub walls. Also, Corona will continue with the structural steel installation for the entirety of this week and next. Finally the conduit for the feeders should finish up early this week.

The focus at LINAC during the beginning of the week will be tying up loose ends. T. Gerding will finish placing the slab rebar and working on the slab edge form. Also the plumbing and electrical rough-in should be complete by the end of day on Wednesday. Then the final slab prep for the under overhang will be completed for the concrete slab pour on Friday, the 25th. Please keep an eye for the concrete trucks in the hospital parking lot on this day.

In the existing Magruder Hall, running wires for J-hooks and installing J-hooks will take place over the next week and a half.

Also, make sure to stay up to date with the 4-week schedule outlook and site photos!